Connect with us

News

SC notices Power Minister and several others over FR petition alleging govt. set to incur loss exceeding Rs 3bn due to irregular tender

Published

on

MINISTER KUMARA JAYAKODY

By A.J.A Abeynayake

The Supreme Court has issued notices to Minister of Power and Energy Kumara Jayakody and several other respondents in connection with a fundamental rights petition alleging that the government is set to incur a loss exceeding Rs. 3 billion due to irregularities in the awarding of a solar power plant tender in Siyambalanduwa, Athimale.

The petitioner claims that the Ceylon Electricity Board (CEB) had called for tenders to construct a 100-megawatt solar power plant, but the contract was awarded to a higher bidder, disregarding the lowest bid, resulting in a significant financial loss to the state. The Supreme Court issued the order on Thursday (20) and directed that notices be sent via courier service by 24 February, at the expense of the petitioner. The decision was delivered by a bench comprising Justices S. Thurairaja and Sampath B. Abeykoon.

According to the petition, a company that offered to supply electricity at USD 0.08 per kilowatt-hour was overlooked in favour of a bidder offering USD 0.122 per kilowatt-hour. The petitioner, Milinda Prasanna Madugalla, stated that he learned of the decision through media reports on 21 January 2025. The petition further alleges that the company awarded the contract later agreed to provide electricity at USD 0.08 per kilowatt-hour, but the government had also agreed to cover additional transmission facility costs over a 10-year period, significantly increasing expenditure.

Although the electricity supply cost was eventually reduced, the substantial increase in transmission charges has resulted in an estimated loss of Rs. 3.3 billion to the government. The petitioner argued that this financial burden would ultimately be borne by the public, making the respondents’ actions unlawful and a violation of fundamental rights.

During the hearing, Senior Counsel Suren Fernando, representing the petitioner, urged the court to treat the matter as urgent and allocate an early date for further proceedings. He informed the court that notices had already been issued to all respondents and relevant parties, along with supporting documents.

However, only a Deputy Solicitor General, representing the Attorney General, listed as the 10th respondent, was present in court. The remaining nine respondents or their legal representatives failed to appear.

The Supreme Court has issued notices to Minister Kumara Jayakody, the Ceylon Electricity Board, Rividenavi (Pvt) Ltd, Lakdanavi Ltd, WinSports Ltd, Blue Circle (Pvt) Ltd, Athimale Plantations (Pvt) Ltd, Secretary to the Ministry of Power and Energy Prof. K.T.M. Udayanga Hemapala, and Cabinet Secretary W.M.D.L. Fernando.



Continue Reading
Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest News

Heat index likely to increase up to ‘Caution level’ at some places in the Northern, North-central, North-western, Western, Sabaragamuwa, Southern and Eastern provinces and Monaragala district

Published

on

By

Warm Weather Advisory
Issued by the Natural Hazards Early Warning Centre at 3.30 p.m. on 11 April 2026, valid for 12 April 2026

The Heat index, the temperature felt on the human body is likely to increase up to ‘Caution level’ at some places in the Northern, North-central, North-western, Western, Sabaragamuwa, Southern and Eastern provinces and Monaragala district.

The Heat Index Forecast is calculated by using relative humidity and maximum temperature and this is the condition that is felt on your body. This is not the forecast of maximum temperature. It is generated by the Department of Meteorology for the next day period and prepared by using global numerical weather prediction model data.

Effect of the heat index on human body is mentioned in the above table and it is prepared on the advice of the Ministry of Health and Indigenous Medical Services.

ACTION REQUIRED

Job sites: Stay hydrated and takes breaks in the shade as often as possible.
Indoors: Check up on the elderly and the sick.
Vehicles: Never leave children unattended.
Outdoors: Limit strenuous outdoor activities, find shade and stay hydrated.
Dress: Wear lightweight and white or light-colored clothing.

Note:  In addition, please refer to advisories issued by the Disaster Preparedness & Response Division, Ministry of Health in this regard as well. For further clarifications please contact 011-7446491.

Continue Reading

Latest News

Sun directly overhead Cheddikulam, Kebithigollewa, Gomarankadawala and Nilaveli about 12:11 noon. today [12]

Published

on

By

On the apparent northward relative motion of the sun, it is going to be directly over the latitudes of Sri Lanka from 05th to 15th of April in this year.

The nearest areas of Sri Lanka over which the sun is overhead today (12th) are Cheddikulam, Kebithigollewa, Gomarankadawala and Nilaveli about 12:11 noon.

Continue Reading

News

CEB orders temporary shutdown of large rooftop solar systems

Published

on

The Ceylon Electricity Board (CEB) has directed owners of large-scale rooftop solar systems to temporarily disconnect their installations for a 10-day period beginning from Friday (April 10), citing growing concerns over grid stability amid low electricity demand and high solar generation.

The directive applies to rooftop solar systems exceeding 300 kW capacity, which are required to remain switched off until April 20. The move coincides with the extended holiday season, during which national electricity demand typically declines, alongside prevailing sunny weather conditions that significantly increase solar output.

Senior electrical engineers told The Island that the decision, though exceptional, was necessitated by operational risks posed to the national grid.

“We are seeing a pronounced imbalance between supply and demand,” a senior CEB system control engineer said. “With industries and commercial establishments operating at reduced levels during the holidays, demand drops. At the same time, solar generation remains high, creating excess power that the grid struggles to absorb.”

He explained that such imbalances could lead to fluctuations in system frequency, potentially threatening the stability of the grid. “If generation exceeds demand, frequency rises beyond acceptable limits.

This can trigger automatic protection mechanisms or, in extreme cases, lead to partial outages.”Another senior engineer attached to the transmission division noted that managing distributed solar generation remains a technical challenge.

“Unlike conventional power plants, rooftop solar systems are not centrally dispatchable. We cannot directly control their output in real time. This limits our ability to balance the system during periods of excess generation,” he said.

He added that the country’s grid infrastructure is still adapting to the rapid growth of renewable energy. “We lack sufficient large-scale battery storage and advanced grid management systems to effectively handle these fluctuations. Until such capabilities are enhanced, temporary curtailment becomes necessary.”

Engineers also pointed out that conventional thermal plants cannot be abruptly shut down or adjusted to compensate for sudden surges in solar generation.

“These plants require minimum stable operating levels. When solar floods the grid during low demand, it creates operational constraints that are not easy to manage,” one official said.

The CEB, in its statement, expressed appreciation for the cooperation of solar system owners affected by the measure, stressing that it is a short-term intervention aimed at ensuring uninterrupted and stable electricity supply across the country.

Energy experts say the development underscores the urgent need for grid modernization, including investment in battery energy storage systems, smart grid technologies, and improved demand-side management.

“This is part of the transition challenge,” an independent analyst noted. “As solar penetration increases, the grid must evolve to become more flexible. Otherwise, curtailment will remain a recurring necessity.”

Despite the temporary shutdown, CEB engineers reaffirmed their commitment to expanding renewable energy.

“Solar power is a key pillar of Sri Lanka’s future energy mix,” a senior engineer said. “But integration must be carefully managed. Grid stability cannot be compromised.”

The temporary disconnection order, which took effect yesterday, marks a critical moment in Sri Lanka’s energy transition—highlighting both the progress made in renewable energy adoption and the technical hurdles that remain.

By Ifham Nizam

Continue Reading

Trending