Connect with us

Features

Mandate of Ministry of Power – Some ambiguities, conflicts and barriers

Published

on

By Dr. Janaka Ratnasiri

The Gazette Notification Extraordinary No. 2187/27 of 09.08.2020 stipulates the mandates of ministries, both Cabinet and State, and the institutes coming under their purview. One common requirement of these mandates is that they should align with the President’s policy document “Vistas of Prosperity and Splendour (VPS)”. In assigning functions among ministries, one deviation from the past practice hitherto followed is the division of Ministry of Power and Energy into two separate ministries, Ministry of Power and Ministry of Energy. There is some sense in this decision (See also The Island of 14.08.2020). It is hoped this change is for the better and not for the worse, as usually happens.

MANDATE OF MINISTRY OF POWER AND STATE MINISTRY OF RENEWABLE ENERGY

The key mandate of the Power Ministry is given as:

Meeting the electricity needs of all urban and rural communities, based on the long-term generation expansion (LTGE) plan prepared by the Ceylon Electricity Board (CEB).

Supplying electricity to business enterprises in Sri Lanka enabling them to be competitive in the global market, and ensuring energy security.

Among the special priority areas identified for the Power Ministry are the following:

Expand the capacity of the Puttalam coal power plant, with additional investment.

Balance the generation mix from renewable energy plants, thermal power plants and natural gas power plants while minimizing the cost of generation and eliminating any uncertainties in generation.

Implement the long-term generation expansion plan.

Improve the efficiency of transmission and distribution systems.

Minimize the cost of electricity for manufacturing industries enabling their competitiveness in global markets.

Special priority areas identified for the State Ministry Renewable Energy, are the following:

Convert the Kelanitissa power plant to a natural gas turbine plant, and expand the Kerawalapitiya power plant.

Develop a smart network ensuring generation efficiency and optimizing its use.

Encourage the use of roof-top solar PV panels in households, commercial establishments and factories, enabling supply of electricity at low cost.

Encourage the private sector and entrepreneurs to establish renewable energy projects.

Add to the national grid the Broadlands Hydropower (HP) plant by 2020, Uma Oya HP plant by 2021, Moragolla HP plant by 2023, Thalapitigala and Seethawaka HP plants by 2024.

Add to the national grid the Mannar 100 MW wind power plant by 2021 and add 800 MW of wind and solar systems set up at Mannar, Pooneryn and Moneragala.

PROVISIONS IN “VISTAS OF PROSPERITY AND SPLENDOUR”

The VPS document has no separate section on Power Sector, but has only a section on Renewable Energy (RE), highlighting the President’s desire to give priority for renewable energy. The preamble to this section says “Renewable energy has now become a widely discussed subject and is needed as part of the overall energy mix of a country, which consists of Hydro, Thermal, Coal and alternative renewable energies. It will ensure that the country has access to low cost energy needed for rapid economic acceleration. By 2030, we expect the country’s renewable energy mix to be 40% of the total portfolio. We also anticipate that hydro and renewable energy together would account for 80% of the overall energy mix by 2030”.

The following targets on power sector development are also given in the VPS document.

According to the current plan, we will take actions to add 230MW of power to the national grid by installing the Broadland hydropower station by 2020, Uma Oya by 2021, Moragolla by 2023, Talapitigala and Seethawaka by 2024.

Immediate actions will be taken to convert the Kelanitissa plant to a natural gas turbine plant, where similar two plants will be implemented in Kerawalapitiya and Hambantota before 2023.

As part of the environmental-friendly policy, we will convert the fuel-powered plants located around the Colombo area to natural gas turbine plants within the next year.

With respect to transformation towards Renewable Energy, the VPS document says:

We will add 100 MW of wind energy in Mannar by 2021. Additionally, we expect to add 800 MW of solar energy to the national grid by executing a wind and solar power project with a public-private partnership in potential locations around the country including Mannar, Poonareyn and Monaragala.

Roof top solar systems will be encouraged so that households and small businesses wo

uld have access to low cost energy, which will be done in the course of the next five years.

We will remove all impediments and incentivize the private sector and entrepreneurs interested in setting up renewable energy projects i.e. solar and wind, and to this end, the government will provide assistance.

We will also introduce an efficient energy generation programme using industrial waste in each city.

We will introduce new policies and legislation to ensure the efficient use of energy in construction sector.

AMBIGUITY IN TARGETS GIVEN IN THE VPS DOCUMENT

The preamble to the section on Renewable Energy in the VPS document says “By 2030, we expect the country’s renewable energy mix to be 40% of the total portfolio. We also anticipate that hydro and renewable energy together would account for 80% of the overall energy mix by 2030”. There is much ambiguity in this statement. Firstly, it is not clear what is meant by “total portfolio”. Secondly, it is not clear whether the term “overall energy” means energy consumed in all sectors including power, transport, industries, commercial and households or whether it means energy consumed in the power sector only. On the face of it, overall energy would mean the former.

But the State Minister of Solar Power, Wind and Hydro Power Generation Projects Development was heard over the TV recently saying that his Ministry’s target is to generate electricity up to 80% of the total electricity generation from renewable energy sources by 2030, in compliance with the VPS document. Obviously, the author of this document has erred when he said that 80% target is in respect of overall energy, if the State Minister’s word is taken as correct.

In an article published by the author in The Island of 19, 20, and 21 of February, 2020, he described, in detail a scheme to meet 80% of the total energy consumption from renewable energy sources by 2030 considering all sectors, including power, industries, transport, commercial and households. The scheme included operating wind power and solar power units as stand-alone systems generating direct current for electrolyzing water and producing hydrogen. There are several options available to use hydrogen to meet the energy needs in power, industries and transport sectors. Another option given in the article is to convert biomass into a liquid fuel for use in transport and households.

Energy generation and consumption data in different sectors in Sri Lanka is given in the Energy Balance Statement (EBS) prepared annually by the Sri Lanka Sustainable Energy Authority (SLSEA). The latest EBS is available only in respect of 2017. Table 1 gives data taken from the EBS and it shows that Sri Lanka has already achieved 45% of renewable energy share in the total energy mix in 2017. Hence, to give a target of 40% to be achieved in 2030 has no meaning.

Table 1 Overall Energy consumption given in 2017 EBSFuelQuantityUnitEnergy Content

(PJ)Share %Petroleum oil 5,375kt232.0 43.9Coal 2,156kt 56.9 10.7Sub-Total (Fossil Fuels) 54.6Major hydro 3,075GWh 30.9 5.8Biomass11,810kt192.9 36.5Other Renewables 1,650GWh 16.2 3.1Sub-Total (Renewables) 45.4Total528.9100.0 ELECTRICITY DEMAND BY 2030

The CEB prepares biennially a long-term generation expansion (LTGE) plan outlining the least cost options of generation plants that need to be added to the system annually for the next 20 years. The latest plan is in respect of the period 2020 – 2039 which is still in the draft form yet to be approved by the Public Utilities Commission, Sri Lanka (PUCSL) and scrutinized by the public. The Plan includes a Base Case that will meet the needs of average demand as well as other cases to meet the needs of high and low demand. Table 2 gives the capacity of different types of generating units that need to be added during 2020 – 2030 as given under Base Case.

Table 2. Capacity additions proposed in LTGE Plan 2020-39Type of plantCapacity to be added during 2020-2030

MWMajor hydropower plants627Solar PV plants900Wind power plants675Biomass plants55Mini-hydro plants165Diesel plants665Gas turbine plants70Combine cycle gas turbine plants1,500New Coal power plants 1,200

The LTGE Plan has also worked out the average generation from each plant type annually and the values obtained for 2030 are given in Table 3, extracted from the data given in Annex 8.4 of LTGE Plan. It is to be noted that it is not possible to forecast exact values for generation from each category in the future because it depends on many extraneous factors such as rainfall, cloud cover, wind regime, fuel prices and demand which are not known accurately in advance. Annex 8.4 gives both average values as well as high and low extreme values anticipated considering the uncertainties. Table 3 gives only the average values anticipated.

It is seen that according to CEB’s LTGE Plan for 2020-39, generation from renewable sources could reach only 35% by 2030, which is far below the 80% target given in President’s VPS Policy Document, assuming what is intended by “total energy” appearing in this document is total electricity generation. In order to align with the President’s policy, CEB will therefore have to come out with a revised plan for capacity additions reducing the thermal plant capacity and correspondingly increasing the RE systems enabling to raise the RE share in total electricity generation from 35% to 80% by 2030.

Table 3. Forecasted average generation in 2030 Plant categoryCapacity MWGeneration GWhMajor hydropower plants1,607 4,364Other renewable energy plants2,700 6,738Sub-total – RE sources4,30711,102Reciprocating plants 136 413Existing coal power plant 810 4,781Existing combined cycle plants 594 1,825New gas turbine plant 70 113NG combined cycle plants 1,500 5,783New coal power plants1,200 7,721Sub-total – Thermal4,31020,636Total31,738Share of RE generation35.0%

OPTIONS FOR MEETING THE PRESIDENT’S TARGET

The obvious choice for meeting the President’s target is to shift from coal power to solar and wind power. In an article written by the author appearing in the Island of July 31st and August 1st, 2020, he showed that by shifting from coal power to solar and wind power, CEB can save over 100 billion rupees annually. This is based on the price of LKR/kWh 10 offered in an on-going wind power project and bids received for solar power projects as divulged by CEB Chairman (Island of 24.07.2020). This is much less than the average cost of generation incurred by CEB which is LKR/kWh 23. In addition to the expenditure saved, adopting solar and wind power gives a bonus of providing pollution free generation.

Several proposals for building large scale solar power plants and wind power plants have been granted Cabinet approval in 2016 and 2017, but there have been no follow up measures taken to pursue them by the CEB. This is despite their economic and environmental advantages. With the announcement of President’s policy on promoting renewable energy, it is hoped that the officials in the Power Ministry and CEB will change their mindset and implement the proposed RE projects without delay. In order to get the private sector involved in this exercise, the present limitation of 10 MW for the development of RE projects by the private sector has to be removed.

The officials of the Power Ministry as well as of the CEB need to be reminded of the statement “We will remove all impediments and incentivize the private sector and entrepreneurs interested in setting up renewable energy projects i.e. solar and wind, and to this end, the government will provide assistance” appearing in the VPS policy document under Renewable Energy section. It is essential that they change their lackadaisical attitude towards renewable energy, if the President’s targets are to be achieved.

The mandate of the State Ministry of Renewable Energy includes building of large scale solar and wind power plants as priority areas. However, their implementation will be possible only with the concurrence of CEB, which was lacking in the past RE projects. There were also media reports of India offering a large solar park under the International Solar Alliance initiated by the Indian Prime Minister together with the French President at the Climate Change Summit Conference held in 2015. Sri Lanka should accept this offer and accelerate building up its solar power capacity.

Another option available is to increase the large hydropower capacity. The general thinking on this is that there are no more suitable sites available to build large hydropower plants in Sri Lanka. However, it is possible to build a large hydro power plant by building a new reservoir on Kotmale Oya below St. Clair’s waterfall and linking it to the existing shaft of the Upper Kotmale Power Plant. This will enable it to operate during the day increasing its plant factor rather than operate only as a peaking plant as done now. Water spilling over the Upper Kotmale Reservoir as well as water flowing down Devon’s water fall can be collected in this new reservoir.

This proposal was made by the Central Engineering Consulting Bureau (CECB) during the planning stage of Upper Kotmale project but not accepted by the Japanese Contractors. It has the potential to add about 160 MW of capacity, generating additional 520 GWh of RE annually. This is a better option than diverting water from Pundalu Oya to the shaft of the Upper Kotmale Project as proposed by CEB in its 2020-39 Plan.

The CEB’s LTGE Plan has given low priority for biomass power plants, adding only 5 MW capacity annually. This can be easily enhanced by setting up dedicated energy plantations and mixed plantations which will generate more renewable energy. It will also provide more opportunities for income generation to rural people and providing fodder to maintain a livestock industry. The colossal sum of money spent annually on importing fuel for thermal power plants presently could be retained in the country by developing biomass power plants.

It has been estimated that 1 ha of dedicated plantation of a crop such as gliricidia will yield 10 t of biomass annually. Assuming combustion of 1 t of biomass with 33% efficiency will generate 1.5 MWh of electricity, 1 ha of plantations has the capacity to generate energy equivalent to 15 MWh. Hence, to replace 1 MW of thermal power plant, about 500 ha energy plantations are required. This could be on new land or on home gardens and abandoned cropland including fallowed paddy land.

In 2019, the Cabinet declared 2022 as the year of Biomass Energy with the objective of promoting energy generation from biomass. Already, SLSEA is pursuing a project funded partly by UNDP and FAO for “Promoting Sustainable Biomass Energy Production and Modern Bio-Energy Technologies” with the specific objective of removing obstacles to the realization of sustainable biomass plantation, increase of market share of biomass energy generation and adoption of biomass- based energy technologies in Sri Lanka. Currently, a survey is planned to identify land available and suitable for energy plantations. Findings of this study will help developing more biomass power capacity at commercial scale by 2030.

CONFLICT BETWEEN THE POWER MINISTRY MANDATE AND VPS POLICY DOCUMENT

The Power Ministry mandate has the following provisions pertaining to the LTGE Plan and Puttalam Coal power plant.

Meeting the electricity needs of all urban and rural communities based on the long-term generation expansion (LTGE) plan prepared by the Ceylon Electricity Board (CEB).

Expand the capacity of the Puttalam coal power plant with additional investment.

Implement the long-term generation expansion plan.

As mentioned previously, CEB’s current plan envisages building 1,200 MW of coal power plants by 2030. Though it is consistent with the above mandate of the Power Ministry, its implementation will result in achieving only 35% share for RE plants out of total generation by 2030. This is in violation of the VPS targets. Hence, either the State Ministry should pursue more RE projects disregarding what was specified in the CEB’s LTGE Plan or the CEB revise its Plan to align with the President’s VPS document.

The VPS document has the following statement:

As part of the environmental-friendly policy, we will convert the fuel-powered plants located around the Colombo area to natural gas turbine plants within the next year.

It is gratifying to note that the new Government has decided to adopt an environment-friendly policy. However, it should apply not only to Kelanitissa Complex, but also to Puttalam Power Plant as well where the pollution is much severe than at Kelanitissa, particularly arising out of million tonnes of ash accumulated over the years containing many toxic heavy metals including mercury and arsenic.

Hence, in keeping with this policy, the proposal to add another 300 MW coal power plant to Puttalam Complex should be scrapped and instead the government should build a NG operated power plant of similar capacity which will be cheaper and easier to operate and maintain. Further, it will not emit any polluting gases such as Sulphur Dioxide or any particulates or any ash at all. Even the emission of other gases such as Carbon Dioxide contributing to global warming and Oxides of Nitrogen will be very much less.

Also, the LTGE Plan is highly flawed. It is supposed to determine which power technology will be the cheapest in 20 years hence based on current prices. With the cost of generation depending on plant capital cost and fuel prices both of which could vary widely within a span of 20 years, it is futile to make forecasts now as to which technology is the cheapest in 20 years hence and to adopt it. The technology should be selected after calling for bids for different technologies and selecting the most economic plant that meets detailed performance specifications as well as specifications on emission limits. This should be done at the time of building the plant and not based on flawed forecasts. Hence, stipulating a mandate to follow a flawed plan does not make sense.

BARRIERS AGAINST THE STATE MINISTRY AND VPS MANDATE

The State Ministry mandate has the following requirement:

Convert the Kelanitissa power plant to a natural gas turbine plant, and expand the Kerawalapitiya power plant.

The VPS document has the following requirements:

Immediate actions will be taken to convert the Kelanitissa plant to a natural gas turbine plant, where similar two plants will be implemented in Kerawalapitiya and Hambantota before 2023.

As part of the environmental-friendly policy, we will convert the fuel-powered plants located around the Colombo area to natural gas turbine plants within the next year.

Conversion to natural gas operation is possible with gas turbine power plants, both open cycle gas turbines (OCGT) and combined cycle gas turbines (CCGT). The latter comprises of two generating units, a gas turbine and a steam turbine which operates with hot exhaust gas released by the gas turbine without consuming additional fuel. Hence, a CCGT plant has a high efficiency exceeding 50%.

At Kelanitissa Complex, there are two OCGT plants with capacities 80 MW and 115 MW commissioned in 1981/82 and 1997, respectively, and two CCGT plants with capacities 165 MW and 163 MW commissioned in 2001/03 and 2003, respectively. All these power plants currently operate with auto diesel, except that the CEB owned 165 MW plant operates partly with diesel and partly with naphtha produced as a surplus in the refinery. All these plants can be converted to operate with NG after modifying their fuel injection systems, if it is found economical to do so considering their age. However, the non-availability of NG is a barrier to convert them within the specified time targets given in the mandates.

In order to convert these gas turbine plants to operate on NG, first NG will have to be imported in the form of liquefied natural gas (LNG) for which special unloading jetties on land or floating units need to be built which takes several years. Though negotiations were held with India and Japan for several years after signing memoranda of understanding with them for building a terminal and importing LNG, no progress has been made public on this project. It was also reported in the media that CEB is seeking assistance from the Asian Development Bank (ADB) to establish a terminal for importing LNG.

Originally, the Ministry of Petroleum had the mandate for importing LNG, but because of the ministry’s inaction, the CEB obtained Cabinet approval for them to import LNG directly. However, under the new government, all matters relating to petroleum including NG comes under the purview of the Ministry of Energy. It is to be seen how the two ministries will coordinate to supply NG for operating not only these existing gas turbine power plants but also the proposed new gas turbine power plants. Importing of LNG needs to follow international protocols and has to be handled by competent operators after having in place the necessary regulatory framework on safety aspects and issuing licenses for operators.

CONCLUSION

The mandate given to the Ministry of Power recommends the establishment of coal power plants in keeping with the long-term generation expansion plan of CEB. On the other hand, the mandates given to the State Ministry for Renewable Energy recommends conversion of existing thermal power plants to operate on natural gas in keeping with the environment-friendly policy of the government. Therefore, to be consistent in applying this policy, the proposed 300 MW coal power plant to be built at Puttalam should also be converted into a gas power plant.

This could be best done by expediting the building of the 300 MW gas power plant at Kerawalapitiya for which the Cabinet approval has already been granted after a procurement process which got dragged for nearly 4 years. This plant, which could be built much faster than the coal power plant, will be able to meet any power deficit anticipated in a few years’ time. It appears that the Ministry is holding back this project for reasons best known to them and the new Minister should use his good office to expedite the project without listening to officials who were responsible for delaying it. The most practicable way of achieving these targets is to appoint a new set of young honest officers not allergic to renewable energy and gas power to take decisions on these matters.

 



Features

Why spill water and reject sunlight while burning imported fuel?

Published

on

Sri Lanka needs a fairer and more transparent approach to renewable energy

by K R Pushparanjan

Sri Lanka has spent several decades encouraging private investment in renewable energy. Small hydropower was among the earliest successes of this policy while rooftop solar has more recently enabled thousands of ordinary households and businesses to become electricity producers. These developments have reduced the country’s dependence on imported fuel, mobilised private capital for electricity generation and contributed towards a cleaner and more diversified energy system.

It is therefore difficult to reconcile these objectives with reports that renewable generators are increasingly being required to curtail production during periods of low electricity demand, particularly on Sundays, Poya days and other holidays. The question is especially relevant to run-of-river mini-hydropower, where naturally available water may simply pass downstream when generation is stopped, and to rooftop solar, where abundant midday sunshine cannot be postponed until the evening peak.

There are, of course, legitimate technical reasons why the Ceylon Electricity Board (CEB), as system operator, may occasionally have to curtail renewable generation. An electricity system must maintain a continuous balance between generation and consumption. On Sundays and holidays, industrial and commercial demand can fall considerably while solar, hydro and wind generation remain available. Certain conventional generating units may sometimes have to remain connected to provide frequency control, voltage support, operating reserves and other services essential for grid stability. Transmission constraints can also make it impossible to substitute generation in one part of the country directly for generation elsewhere.

No responsible renewable-energy producer would suggest that grid security should be compromised merely to accept every available unit of renewable electricity. However, legitimate engineering considerations should not become a blanket explanation that places curtailment decisions beyond public scrutiny.

The CEB itself describes the economic principle underlying electricity dispatch as merit-order dispatch, under which lower-cost generation is normally utilised before progressively more expensive generation. Consequently, whenever inexpensive renewable electricity is deliberately curtailed while substantially more expensive oil-fired generation continues, electricity consumers and renewable producers are entitled to ask why. If a particular thermal generating unit must remain online for frequency stability, voltage support, network security or some other technical requirement, that can be explained. If transmission congestion requires renewable generation in a particular area to be reduced, that too can be demonstrated. Transparency should strengthen technically sound decisions, not threaten them.

Mini-hydro and an unequal contractual relationship

Run-of-river mini-hydropower deserves particular consideration. Unlike reservoir hydro, most such plants have limited ability to store water. When sufficient water is available, but the plant is instructed not to generate, that water may simply bypass the turbines and continue downstream. The opportunity to produce that electricity is then lost. No imported diesel, furnace oil or coal is required to allow that water to turn a turbine, and there is no corresponding fuel-related foreign-exchange expenditure.

Sri Lanka’s mini-hydropower industry was developed largely through private investment. The CEB currently records 219 commissioned mini-hydro projects with an aggregate capacity of approximately 430 MW and acknowledges the role of government policy in encouraging private-sector development of this indigenous renewable resource.

Yet, there has always been a fundamental imbalance in the commercial relationship between the small power producer and the national purchaser. Mini-hydro projects have historically sold their electricity through the Standardised Power Purchase Agreement (SPPA). The very nature of a standardised agreement substantially limits the individual developer’s negotiating position. Published material concerning Sri Lanka’s small-power-producer framework has described the SPPA as standardized and non-negotiable.

This is hardly a negotiation between parties of equal bargaining strength. A mini-hydro developer cannot realistically reject an unfavorable provision and offer the electricity to another national grid. For much of the industry’s history there has effectively been one purchaser, leaving the developer with little practical alternative but to accept the terms offered.

The weakness of that position becomes particularly evident when curtailment occurs. A PUCSL-commissioned study has recorded that under the original SPPA there was no penalty on the CEB for not purchasing energy. The developer may have invested the capital, borrowed the money, undertaken the construction and hydrological risks, maintained the machinery and had both water and generating equipment available, yet still carry the financial loss when electricity cannot be accepted for reasons originating within the national system.

If curtailment is genuinely necessary for grid security, the plant operator may have to accept the technical instruction. It does not logically follow, however, that the entire financial consequence should automatically be imposed upon the weaker contracting party.

Germany curtails renewables too – but differently

Germany provides a useful comparison precisely because it demonstrates that renewable curtailment is sometimes unavoidable even in an advanced electricity system. With very large quantities of wind and solar generation, Germany regularly experiences transmission congestion and occasions when all available renewable electricity cannot immediately be transported to consumers.

The important difference lies in how the problem is managed. Germany operates a regulated redispatch system. European electricity-market rules require redispatch to be undertaken according to objective, transparent and non-discriminatory criteria. Conventional generation, renewable generation and storage can all form part of the process, with interventions determined by what is required to relieve network constraints safely and economically.

Equally important is the recognition that curtailment has financial consequences. Germany’s Federal Network Agency explains that affected generators and storage operators have statutory entitlements to appropriate financial compensation within the redispatch framework. Depending upon the circumstances, relevant arrangements can take account of generation expenditure, lost revenue opportunities, readiness costs, maintenance implications and costs avoided because generation was reduced. The German framework also provides balancing mechanisms intended to address the commercial position of installations affected by redispatch, including renewable generators.

The principle is worth considering in Sri Lanka. When a privately financed generator is required to sacrifice otherwise available production for the security and benefit of the national electricity system, why should that cost automatically and entirely be borne by the generator?

Germany offers another lesson that may be even more important: transparency. Through the Federal Network Agency and its SMARD electricity-market information platform, information on congestion management, renewable curtailment and conventional redispatch is publicly available. Official German figures show that renewable curtailment amounted to approximately 3.5 percent of renewable generation in 2025, meaning that more than 96 percent of renewable electricity generated reached the system and consumers.

Sri Lanka cannot simply copy Germany. The two electricity systems differ enormously in size, resources, interconnections and market structure. What can be adopted, however, are the principles of transparency, non-discrimination, accountability and fair treatment of generators affected by decisions taken for the benefit of the wider system.

What generation remained online?

Whenever significant renewable curtailment occurs in Sri Lanka, sufficient information should therefore be made publicly available to answer some straightforward questions. How many megawatts were curtailed, for how many hours, and how many megawatt-hours of renewable electricity were consequently lost? Which thermal generating units remained operational during those hours? What fuel were they using and what was their approximate generation cost? Why was each of those units technically required to remain online? Was the curtailment caused by system-wide oversupply, a local transmission constraint, frequency considerations or some other identifiable requirement? These are not unreasonable questions. If the decisions are technically and economically sound, the answers should vindicate the system operator.

The issue assumes particular importance because Sri Lanka has historically spent enormous sums purchasing thermal electricity. An Auditor General’s special audit concerning ACE Power Embilipitiya reported expenditure of approximately Rs. 59.454 billion on electricity purchased from that plant between 2016 and 2021. The audit also drew attention to transmission-system problems and the consequences of permanent solutions not being implemented in a timely manner.

This does not establish that thermal generation is unnecessary or that private thermal producers have acted improperly. Nor should allegations of corruption be made against particular parties without evidence. Nevertheless, Sri Lanka’s long history of public concern regarding procurement, governance and major public expenditure makes transparency particularly important. Large thermal power contracts, fuel purchases and capacity arrangements involve substantial sums of money. The best protection against suspicion is not secrecy but disclosure.

If expensive thermal generation genuinely has to remain online while inexpensive renewable generation is curtailed, publish the technical reason. Publish the quantities. Publish the relevant costs. Allow engineers, economists, regulators, investors and electricity consumers to examine the decision for themselves.

Rooftop solar must not become the next casualty

The same argument now applies to rooftop solar. Sri Lanka successfully encouraged households and businesses to invest their own money in solar installations. Net Metering, Net Accounting and related arrangements helped transform consumers into small-scale electricity producers and contributed substantially to the growth of distributed renewable energy. PUCSL continues to recognise Net Metering, Net Accounting and Net Plus within Sri Lanka’s rooftop-solar framework.

The rapid expansion of rooftop solar undoubtedly creates genuine technical difficulties. Solar production is concentrated around daytime hours, while Sri Lanka’s major electricity demand peak occurs later. On a sunny Sunday or holiday, solar production can therefore be substantial precisely when commercial and industrial demand is low. Distribution networks designed for one-way electricity flows may also encounter voltage and hosting-capacity limitations as increasing quantities of electricity flow back from consumers towards the grid.

But it would be fundamentally unfair to encourage citizens to invest their savings in solar energy and subsequently treat their electricity as a problem simply because the national grid has not developed quickly enough to accommodate it.

Battery energy storage offers an important part of the eventual solution. A household battery can capture surplus solar energy around midday and release it during the evening, when both the household and the national system need electricity most. PUCSL has already recognized the value of combining rooftop solar with battery storage in its evolving regulatory arrangements.

However, domestic battery storage still represents a considerable additional investment for an ordinary household. Public policy should therefore be careful not to make battery ownership an economic prerequisite for participating in rooftop solar before such systems become reasonably affordable.

Until domestic battery storage becomes economically accessible to the average household, Net Metering and Net Accounting should be preserved, strengthened and made genuinely accessible. They provide a practical bridge between today’s rapidly growing distributed solar generation and tomorrow’s electricity system in which affordable batteries, utility-scale storage, pumped hydro and sophisticated demand management can shift much more renewable energy from periods of surplus to periods of high demand.

The national grid should, during this transition, continue to perform an important balancing function. Meanwhile, policy should encourage rather than compel household batteries through appropriate time-of-use tariffs and incentives. As battery prices decline, consumers will increasingly adopt them voluntarily because the economics make sense.

The grid must evolve with renewable energy

The longer-term answer is therefore not to choose between renewable energy and grid stability. Sri Lanka needs both.

Investment is required in battery storage, pumped-storage hydro, stronger transmission and distribution networks, better renewable forecasting, modern inverter technology, sophisticated system-control facilities and demand-response programmes. Electricity tariffs can also be designed to encourage industries, commercial establishments, water pumping, electric-vehicle charging and other flexible loads to consume more electricity during periods of abundant solar production.

The electricity system must gradually become capable of moving energy not merely geographically but also across time—storing electricity when nature provides more than consumers require and releasing it when demand rises.

This is also essential for maintaining investor confidence. Private investors make renewable-energy decisions according to expected annual generation, financing costs and anticipated revenue. If a developer can spend substantial capital constructing a renewable project only to face unpredictable curtailment outside his control and without adequate compensation or contractual recourse, the investment risk increases. Eventually that risk translates into higher financing costs, higher required returns and fewer projects.

A country cannot credibly invite private investors to finance renewable energy infrastructure while retaining an overwhelmingly one-sided contractual ability to discard their output and transfer the resulting financial loss back to them.

Transparency should not frighten the CEB

Nobody should expect the CEB to compromise national grid security merely to accommodate a mini-hydro plant or rooftop-solar producer. Where curtailment is technically unavoidable, it should occur.

But “system stability” should never become a phrase that ends the discussion.

Where synchronous generation must remain operating, explain why. Where transmission congestion requires renewable curtailment, identify the constraint. Where renewable producers sacrifice available generation for the benefit of the national system, develop a fair compensation mechanism. Where expensive thermal generation remains operational while naturally available water bypasses turbines, disclose why that was the technically necessary and economically preferable decision.

Germany demonstrates that renewable curtailment and renewable-energy development are not contradictory. Even sophisticated electricity systems sometimes have to discard renewable electricity. The difference is that a mature system attempts to minimize curtailment, operates under transparent rules, publishes relevant information and recognizes the financial consequences imposed upon generators.

Sri Lanka should aspire to the same principles.

We should not encourage private investors to build mini-hydropower plants and then place them against the wall through contracts over which they have little negotiating power. We should not encourage households to spend their savings installing solar panels and later make them bear the cost of deficiencies in the electricity network. And we should certainly not discard economically usable indigenous renewable energy without a convincing explanation while scarce foreign exchange is being spent importing fuel.

Sri Lanka should not spill usable water, reject available sunlight and then burn imported fuel to produce electricity that nature was prepared to provide without a fuel bill.

The issue is not whether every unit of renewable electricity can always be accepted. Clearly it cannot. The real test is whether every unit curtailed was genuinely necessary, whether the least-cost and least-wasteful solution was chosen, whether affected producers were treated fairly, and whether the public is permitted to see the evidence.

That is not an unreasonable demand from renewable-energy producers. It is the standard of transparency, accountability and economic discipline that Sri Lanka’s electricity consumers should expect from a modern national power system.

Continue Reading

Features

‘Career of Evil’

Published

on

Tales of Mystery and Suspense 22

by Prof. Rajiva Wijesinha

I return now to J K Rowling of Harry Potter fame, writing under the pseudonym Robert Galbraith about Cormoran Strike. There are several books in this series of off-beat detective stories, featuring a private investigator who lost a leg while serving in the army, and his assistant Robin Ellacott, who had been raped when a student, with lasting psychological effects. Strike himself was the child of a rock band groupie, who had lived a sordid life, her last attachment being to a failed rock star of relatively aristocratic provenance and brutal habits.

Career of Evil is the third in the Strike series, and markedly different from the two books I read previously, the first and the fifth. Those were relatively speaking classic whodunnits, with a range of possible murderers, the solution in the end being quite unexpected but also convincing. The murderers in both cases are unhinged, but this does not become obvious until Strike has put two and two together and revealed a history of aberrant behaviour.

This novel has just a few suspects, all of them bizarre, as is made clear from the moment they are introduced. The case begins with Robin being sent a severed leg from a dead body, or rather it begins with the thoughts of the murderer who seeks revenge from Strike, which it seems he intends to achieve by first terrifying and then killing the woman he calls Strike’s Secretary. He also evinces a horrid desire to mutilate women after abusing them.

The first person Strike thinks of as a possible suspect is a member of a crime syndicate known to have sent body parts through the post, but Strike soon decides that he cannot be the perpetrator, in part because he is not likely to have known that Strike was responsible for his conviction earlier. Rather Strike is convinced it is one of three people who hate him, two of them individuals he helped to prosecute when he was in the investigating unit of the army, the third his step-father whom he suspected had killed his mother.

Unfortunately, Wardle, the policeman assigned to the case, who gets on well with Strike, is convinced it is the first person Strike had suggested, and does not seem interested in the rest, so Strike sets about trying to find out what they are up to.

They are not easy to trace, but Strike eventually tracks them down. He finds Laing’s mother in Scotland, although she is no longer able to provide any useful information. He then tracks down the mother of Laing’s first wife, Rona, whom Strike had found tied up and tortured. It was this incident that led to Laing’s conviction and imprisonment, and ultimately fuelled his hatred of Strike.

He finds the sister of the second suspect, Noel Brockbank, and learns that she and her brother were both abused as children by their stepfather. Brockbank later went on to abuse young girls himself. When Strike went to arrest him over the abuse of his stepdaughter, Brockbank attacked him with a broken bottle, and Strike knocked him out. Brockbank subsequently suffered seizures and was found to have a serious brain injury. Although Strike was initially blamed for the injury, it was later established that Brockbank had fractured his skull in a rugby match before the confrontation. Brockbank was therefore never convicted of the abuse allegations, while Strike was cleared of responsibility for his brain injury.

Strike’s third suspect is his former stepfather, Jeff Whittaker, whom he describes as unutterably filthy and abusive, yet strangely attractive to women. When Strike tracks him down, he finds Whittaker living with Stephanie, a woman who supports him with what she earns as a sex worker. Despite being abused by Whittaker, she remains devoted to him.

In his musings, the killer refers to the woman he lives with as “It”, suggesting that he could be Whittaker, who lives off Stephanie’s earnings. But when Robin is attacked by a man dressed differently from Whittaker, whom she had seen shortly before, it becomes clear that Whittaker is not the killer. Laing, the first of Strike’s three suspects, is also apparently ruled out when Robin sees him on crutches and learns that he is claiming disability benefits. Strike and Robin therefore concentrate on the third suspect, Noel Brockbank, whom they eventually trace to a home he shares with his girlfriend, Alyssa, and her two young daughters. Robin has seen the younger girl and becomes increasingly worried about what Brockbank might do to her. Although Strike has ordered her to leave Brockbank alone, Robin continues investigating because of her concern for the child. She eventually discovers that Brockbank has been sexually abusing the older of the two girls.

Meanwhile, Strike and Robin manage to identify the girl whose leg was sent to the agency. Among the bizarre letters Strike had received in the past was one from a young woman who fantasizes about having her healthy leg amputated and believed that Strike had deliberately had his own leg removed. Robin realises that the girl was suffering from a condition known as body integrity identity disorder, or BIID, in which a person has a persistent desire to have a healthy limb or other body part removed. Strike simply ignored the letter, unaware that the girl was suffering from a recognised condition and that her request was serious. The girl, Kelsey Platt, is subsequently found to have been murdered, and the police discover forged letters apparently written by Strike in response to her.

Wardle has his suspicions of the man married to the girl’s sister, with whom she had lived. Strike thinks this absurd, and it turns out that the man has an alibi for the time of the murder, but Strike does go along when the sister asks to see him and is overwhelmed by the sense of grief she and her husband evince.

The girl is evidently a godsend to the murderer, whose desire to remove body parts could not be controlled. He chops fingers off a girl he almost kills, and then removes the nose and ears of a girl he kills soon afterwards. And previously he had sent Robin the toe of the girl whose leg had been sent earlier.

All this horror can seem over the top, and one may wonder how Rowling could bring herself to wallow in such grim material. But perhaps she felt very strongly about the abuse women were subject to, and though her depiction of the way women played into the hands of abusive men seems excessive, she feels that awareness of that increases the need for support groups and other mechanisms to provide safety nets.

But there is also another side to the novel, namely the relationship between Strike and his partner Robin, which verges on the romantic though neither wishes to move on the matter. Strike feels diffident about taking advantage of his position as her employer, while Robin is engaged to a young man she has known for years, and whom she was virtually engaged to while at university. He has stood by her after the rape, when she could barely face society, and she finally decides to accept him and they are planning their wedding at the beginning of this book. But she finds that he is jealous of Strike, and hence his resentment of her commitment to her work, she breaks off the relationship when they are staying with her parents to finalize arrangements for the wedding.

But they still share a flat, and given the threat looming over her she cannot really move to live by herself. And gradually his misery wears her determination down, and she agrees again to marry him. The novel ends with their wedding, which Strike just manages to get to, causing her to beam, though she ‘had not once smiled in the entire service’.

But they still share a flat, and with the threat hanging over her, Robin cannot really move out and live by herself. Gradually, Matthew’s misery wears down her determination, and she agrees to marry him after all. The novel ends with their wedding. Strike arrives just in time, battered and bloodied after his confrontation with the killer. Robin has not smiled once during the ceremony, but when she sees Strike, she suddenly beams.

Before that, in the kerfuffle caused by Robin’s attempt to rescue the children of the woman Brockbank was living with, Strike sacks her. This turns out to be useful to him, because he subsequently enlists the children’s mother, Alyssa, to help trap the killer, whom he has by then identified as Donald Laing. With Shanker’s help, Strike arranges for Alyssa to pose as his new secretary and lure Laing into the open while he gains access to the flat Laing has been using as a hideout. There he discovers the evidence of the murders, including the severed body parts kept in a refrigerator.

This leads to a dramatic climax in which the murderer turns up. Strike has difficulty subduing him, partly because of his missing leg, but he is helped by Shanker, a man whom his mother, Leda, had taken in as a neglected and badly beaten boy and who has remained deeply grateful to the family. With the murderer captured and the case effectively wrapped up, Strike asks Shanker to drive him to Yorkshire, where Robin’s wedding is taking place. They arrive while the ceremony is still in progress, and Strike manages to get into the church just as Robin is making her vows. When she sees him, she beams and says “I do” while looking at him rather than at Matthew.

Clearly, this suggests that the relationship between Strike and Robin is far from settled. Indeed, as I discovered when I read the fifth book in the series, the story certainly does run and run.

Continue Reading

Features

Ananda Ganegoda: Pioneer in popularising Sinhala music

Published

on

Ananda Ganegoda

by Dr Upul Wijayawardhana

It was with a great sense of sadness that I received the news about the death of Ananda Ganegoda at the age of 80 years; the last of the famous industrialist Ganegoda brothers to depart. Ananada was a businessman par excellence but he ought to be remembered specially for his outstanding contribution to popularising Sinhala music by founding the music label Singlanka in 1980. Unfortunately, I lost touch with him, having seen him only once since I left Sri Lanka in May 1988. As I mentioned in my article on statins (Cholesterol lowering statins: Scope for use widens – The Island; 18 September) I have met some remarkable people in my practice of medicine and Ananda was certainly one of them.

The Ganegoda brothers were actually two sets of first cousins though they worked as a single family. Nandajeewa, Sumanalatha, Wimalajeeva, Karunajeewa and Ratnajeeva were the children of Jineris Ganegoda whilst Chandrasiri, Jinadri and Ananda were the children of Jineris’ younger brother Johanis. Sadly, it seems to have been forgotten by many that the Ganegoda brothers were instrumental in changing our export economy by starting garment factories in 1954, one of the first groups of non-traditional exports. According to a family post on Facebook, the visionary leader was Wimalajeewa, who started Noortex, Mayura, GIL and Eurolanka garment factories. Others followed suit and they presided over a vast business empire.

My first contact was not with Ananda but Karunajeeva, if my memory serves me right. After a consultation and a friendly chat, he invited me to a factory visit, which I readily agreed to. He took me to one of the factories in Ratmalana and I was very pleasantly surprised with the high standards maintained in the factory including workers’ welfare. I was able to taste the delicious food served to the workers. The icing on the cake was his measuring me out for shirts and trousers which I wore for a very long time!

Maybe around late 1983 or early ‘84, Ananda ‘channelled’ me for a consultation in the Central Hospital for chest pain and was accompanied by his wife, Nandani. I noted that, in addition to the cigarette smell, he had heavy nicotine staining of fingers. After having ensured that his pain was not cardiac, I tore into him stating, “What is wrong with you? You are among the Sri Lankan businessman doing well and you seem determined to commit suicide with chain smoking,” Then I started wondering whether I had been too blunt, but Ananda said “Dr, Thank you very much. I will stop smoking” and his calm response took me by surprise. On a subsequent social occasion, Nandani whispered in my ear that he had an occasional ‘secret smoke’ and when I encountered, Ananda said “Dr, hari amarui” but promised he would give up completely. I do not know whether he did so but the significant reduction of consumption, hopefully, contributed to his longevity.

I met him last in 1995, in the role of a peacemaker when he was in open conflict with a close relative of mine. I pleaded with him to stop the battle, pointing out that one of his nieces was being courted by the son of my relative. Though shocked, he promised to make peace.

Ananda’s crowning achievement was the founding of Singlanka which made Sinhala songs accessible to the masses. Those of us, old enough to remember, know how difficult it was to listen to music. As a child, I had to go to the village Community Centre to listen to the radio, which is in utter contrast to what is happening today. With just a click on the smartphone anyone can listen to music of any choice, anytime, anywhere as long as you are connected to the internet! Recording with the ability to playback, started with the Phonograph invented by Thomas Edison in 1877, Vinyl records being available from the early twentieth century. They came in various speeds and sizes but needed cumbersome players.

The real breakthrough came in 1963, when the Dutch company Philips introduced the Compact Cassette with more convenient players. Singlanka gave everyone the opportunity to listen to their favourite artists on Compact Cassettes. When the Compact Disc format, developed jointly by Philips and Sony, released in 1983, gathered momentum, Singlanka too moved to this format but most of us are still in possession of Singlanka cassettes. I still occasionally listen to Nanda Malini’s “Pavana”, which has become relevant because of the recent death of Nanda Malini and the ascent of JVP to power, but that is another story.

Most of our famous singers, including the greats like Amaradeva and Nanda Malini, owe at least a significant part of their fame and fortune to Singlanka, which was Ananda’s brainchild. Looking at the discography of Singlanka is like looking at a list of all favourite singers. In addition, Ananda gave the opportunity to the less known in the field of music also to showcase their talent, the best example being Carlo Fonseka’s Calochita Gee, which was a compilation of songs sung by various artists to the lyrics and melodies of Carlo. Who would have imagined multi-talented Carlo having musical creativity as well!

As for me, one event illustrated his generosity and his sense of gratitude. When Dr N J Wallooppillai retired, and I succeeded him as Cardiologist, I arranged for an international conference “Cardiology Update”, which was held on 6th and 7th of June 1985 at Galadari Meridien Hotel, culminating in a banquet. When I rang Ananda about this, he immediately offered to sponsor music for the evening and arranged for Patrick Denipitiya Combo to play and Ivor Dennis, Indrani and Sisira Senaratna to sing. It was a memorable evening, with plaudits from attendees, though we did not have an opportunity to rehearse. I compeered and we selected the songs as we went on. When Indrani wanted to sing Gaya Geethayan I had to stop as it was a Hindi tune and Indians were in the audience! My wife Primrose joined Ivor Dennis to duet “Olu Pipila Wela Lela Denawa”. We ended the banquet with Ivor Dennis singing, and the audience joining, the patriotic song Dakuna, Negenahira, Batahira, Uturada, Eka Kodiye Sevene thanks to Ananda. I am eternally grateful to him.

May Ananda attain the Supreme Bliss of Nibbana!

Continue Reading

Trending