Connect with us

News

Wide ranging rackets benefiting CEB engineers

Published

on

By Ifham Nizam

The Ceylon Electricity Board implements most of its power transmission and distribution infrastructure development projects like the construction of new transmission lines, transmission and distribution substations, etc., using loan funds obtained from international lending agencies such as the Asian Development Bank (ADB) and Japan International Cooperation Agency (JICA).

These “concessionary” loans are guaranteed by the government, and projects funded by those loan packages are implemented through specially set up project management units (PMUs).

Engineers attached to PMUs are given special facilities and monetary incentives on the understanding that they will work outside normal working hours and weekends to complete their projects on time and within the allocated budget.CEB often justifies these projects for priority financing citing “great national importance” and the critical needs to improve the power transmission and distribution infrastructure of the country.

Almost all of these project titles carry the words like “green energy”, “clean energy”, “green power”, etc., signifying these investments are primarily aimed at using renewable energy.

However, according to a senior official of the Ministry of Power & Energy, these projects are seldom completed within the given time period or budget. Because of this reason not only the expected benefits of these investments are often lost to the country, but the government incurs heavy losses by way of commitment fees paid to lending agencies.

Once project funds are committed through a loan agreement, the government has to pay this fee to the lending agency, generally computed as a percentage of the loan amount or the “commitment amount”. It is a significant burden to the government, especially in a situation where there is a severe shortage of foreign currency.

If the loan funds are disbursed within the original term of the loan, this “front end fee” is charged at a lower percentage. Hence, when CEB does not complete projects in time, the government ends up paying a higher commitment fee, and is also forced to seek an extension to the original loan disbursement period, thus incurring further costs.

Even more disturbing than long delays in project completion is that some completed projects have turned out to be wasteful investments of foreign funds given to the country.It is understood that the former CEB Chairman M. M. C. Ferdinando had questioned why the new 132kV transmission line between Ambalangoda and Galle, which was completed in 2017 at a cost of Rs. 1,500 million, remained unserviceable to date.

The Sunday Island understands that CEB’s System Control Center is able to switch on this transmission line only when the Samanalawewa Hydropower Plant is running at full capacity.This project had been billed by CEB’s transmission planners as a high-priority investment and solution for the serious transmission bottlenecks in the southern network of the country. Southern areas had been experiencing serious transmission capacity restrictions for decades.It is understood that the CEB General Manager has responded to the Chairman’s inquiry by stating that the commissioning of several new transmission lines that are presently under construction would make the Ambalangoda-Galle transmission line operational.

The 220kV transmission line from Pannipitiya to Polpitiya via Padukka is another example of a costly planning blunder by the CEB. Construction of this long transmission line commenced in 2015 but was delayed owing to many problems, including public protests and court cases filed by some landowners.However, when this ADB-funded project was eventually completed in late 2021 (after a delay of over five years), it has been discovered the power flows in the wrong direction when the line is switched on, causing overloading of the Pannipitiya substation.Hence, this transmission line also remains idle presently. It is understood that CEB planners have explained that power would flow in the right direction once several other transmission lines (being constructed under different loan packages, and already delayed by many years) are completed.

The then CEB General Manager taking part in a national television discussion following the countrywide power outage on August 17, 2020, explained that the unavailability of this critical transmission line was a major contributing factor to CEB’s inability to restore supply for many hours.Another example of colossal waste of funds is the transmission substation at Kappalthurai in the eastern province that has cost the country over Rs. 2,500 million of ADB loan funds. Since there is no high demand for electricity or no future growth in demand in the area, this installation will be idle for the foreseeable future.

According to CEB employees, the existing Trincomalee substation, which is situated about 11 km from this new substation, has ample capacity to serve the electricity demand in the area for many years to come. In the meantime, CEB has made a large investment in increasing the capacity of the Trincomalee substation as well.It is also understood that CEB’s Projects Division has been maintaining several non-functional PMUs for years, spending large sums of money on rented project offices and large project staff, even when no funding has been secured for relevant projects.

CEB employees complain that project directors and their engineers attached to these “white elephants” are allowed to enjoy all benefits, including project allowance (an additional amount equal to one-third of monthly salary) and luxury SUVs because most of them hold important positions in the powerful CEB engineers’ union.They claim that the CEB management never holds to account any project manager responsible for long delays, but they are allowed to continue to enjoy all the perks. According to a senior engineer who works as a consultant on project-related work, this guarantee of “job security” acts as a strong incentive for the project engineers to prolong their projects.CEB employees believe another reason for this lackadaisical attitude of CEB top management is that foreign-funded projects have long been a steady source of luxury vehicles for CEB engineers.

Most vehicles used by top CEB engineers including the General Manager have been provided under different foreign-funded projects, as the existing government guidelines will not allow the purchase of such high-end SUVs having large engine capacity including premium European makes like Audi and Mercedes Benz for government officials.CEB employees complain that the Ministry of Power & Energy generally turns a blind eye to these irregularities mainly because the majority of project managers and their project engineers are top officials of the powerful engineers’ union.

They allege that even the Public Utilities Commission of Sri Lanka (PUCSL,) which has the legal obligation to ensure CEB will not make unnecessary or wasteful investments in its transmission infrastructure, has never questioned CEB regarding assets that are idling for many years after spending billions of rupees of public money.



Latest News

Speaker of Parliament Asoka Ranwala resigns

Published

on

By

NPP Parliamentarian Asoka Ranwala who was appointed the 22nd Speaker of  Sri Lanka’s Parliament, on 21st November has resigned from his position today [13], in the wake of the controversy surrounding his educational qualifications.

 

Continue Reading

Latest News

Harsha Amarasekera PC appointed Chairman of the Port City Economic Commission

Published

on

By

President Anura Kumara Dissanayake has officially appointed members to the Port City Economic Commission.

Accordingly Harsha Amarasekera, President’s Counsel, has been appointed as the Chairman while Damien Amal Cabraal, Mohan Ray Abeywardena, Sanjaya Kulatunga, and Dr. Harsha Subasinghe were appointed as members of the Port City Economic Commission

The official letters of appointment were handed over to the members by the Secretary to the President Dr. Nandika Sanath Kumanayake at the Presidential Secretariat today (13).

 

Continue Reading

Latest News

“Offenders will face consequences, regardless of rank or status.” – President

Published

on

By

“We will not allow the trust the people have placed in us to be undermined in any way,” stated President Anura Kumara Dissanayake during a meeting with the heads of state media today (13).

He further emphasised, “Regardless of their status in government, if mistakes are made, we will not hesitate to take appropriate action.”

The President further explained:
“For more than seven decades, the people of this nation have built and dismantled various governments. For the first time, we stand with a profound understanding of the historic mandate entrusted to us and the National People’s Power on two occasions.

The people placed their faith in the National People’s Power (NPP) government, hoping for a standardised and stable country. We will not tarnish that extraordinary trust, even by the slightest misconduct.

Simply put, our government is not here to shield anyone who errs, for any reason. Be it within the broader framework of the country or within our administration, anyone found guilty of wrongdoing will face consequences. We will not hesitate to act decisively and at the right time. In essence, our government will not shield anyone who makes a mistake, regardless of the reason. Whether the mistake occurs within the country or at any level within our government, we will not hesitate to take decisive action. Every necessary step will be taken at the appropriate time without delay.”

President Anura Kumara Dissanayake also reaffirmed his government’s unwavering commitment to upholding the trust placed in them by the people, who have endured decades of deception. He pledged to work tirelessly to build a better nation.

The Minister of Health and Mass Media, Dr Nalinda Jayatissa, Director-General of Government Information, Harsha Bandara, and the heads of state media were present at the meeting.

Continue Reading

Trending