News
Wide ranging rackets benefiting CEB engineers
By Ifham Nizam
The Ceylon Electricity Board implements most of its power transmission and distribution infrastructure development projects like the construction of new transmission lines, transmission and distribution substations, etc., using loan funds obtained from international lending agencies such as the Asian Development Bank (ADB) and Japan International Cooperation Agency (JICA).
These “concessionary” loans are guaranteed by the government, and projects funded by those loan packages are implemented through specially set up project management units (PMUs).
Engineers attached to PMUs are given special facilities and monetary incentives on the understanding that they will work outside normal working hours and weekends to complete their projects on time and within the allocated budget.CEB often justifies these projects for priority financing citing “great national importance” and the critical needs to improve the power transmission and distribution infrastructure of the country.
Almost all of these project titles carry the words like “green energy”, “clean energy”, “green power”, etc., signifying these investments are primarily aimed at using renewable energy.
However, according to a senior official of the Ministry of Power & Energy, these projects are seldom completed within the given time period or budget. Because of this reason not only the expected benefits of these investments are often lost to the country, but the government incurs heavy losses by way of commitment fees paid to lending agencies.
Once project funds are committed through a loan agreement, the government has to pay this fee to the lending agency, generally computed as a percentage of the loan amount or the “commitment amount”. It is a significant burden to the government, especially in a situation where there is a severe shortage of foreign currency.
If the loan funds are disbursed within the original term of the loan, this “front end fee” is charged at a lower percentage. Hence, when CEB does not complete projects in time, the government ends up paying a higher commitment fee, and is also forced to seek an extension to the original loan disbursement period, thus incurring further costs.
Even more disturbing than long delays in project completion is that some completed projects have turned out to be wasteful investments of foreign funds given to the country.It is understood that the former CEB Chairman M. M. C. Ferdinando had questioned why the new 132kV transmission line between Ambalangoda and Galle, which was completed in 2017 at a cost of Rs. 1,500 million, remained unserviceable to date.
The Sunday Island understands that CEB’s System Control Center is able to switch on this transmission line only when the Samanalawewa Hydropower Plant is running at full capacity.This project had been billed by CEB’s transmission planners as a high-priority investment and solution for the serious transmission bottlenecks in the southern network of the country. Southern areas had been experiencing serious transmission capacity restrictions for decades.It is understood that the CEB General Manager has responded to the Chairman’s inquiry by stating that the commissioning of several new transmission lines that are presently under construction would make the Ambalangoda-Galle transmission line operational.
The 220kV transmission line from Pannipitiya to Polpitiya via Padukka is another example of a costly planning blunder by the CEB. Construction of this long transmission line commenced in 2015 but was delayed owing to many problems, including public protests and court cases filed by some landowners.However, when this ADB-funded project was eventually completed in late 2021 (after a delay of over five years), it has been discovered the power flows in the wrong direction when the line is switched on, causing overloading of the Pannipitiya substation.Hence, this transmission line also remains idle presently. It is understood that CEB planners have explained that power would flow in the right direction once several other transmission lines (being constructed under different loan packages, and already delayed by many years) are completed.
The then CEB General Manager taking part in a national television discussion following the countrywide power outage on August 17, 2020, explained that the unavailability of this critical transmission line was a major contributing factor to CEB’s inability to restore supply for many hours.Another example of colossal waste of funds is the transmission substation at Kappalthurai in the eastern province that has cost the country over Rs. 2,500 million of ADB loan funds. Since there is no high demand for electricity or no future growth in demand in the area, this installation will be idle for the foreseeable future.
According to CEB employees, the existing Trincomalee substation, which is situated about 11 km from this new substation, has ample capacity to serve the electricity demand in the area for many years to come. In the meantime, CEB has made a large investment in increasing the capacity of the Trincomalee substation as well.It is also understood that CEB’s Projects Division has been maintaining several non-functional PMUs for years, spending large sums of money on rented project offices and large project staff, even when no funding has been secured for relevant projects.
CEB employees complain that project directors and their engineers attached to these “white elephants” are allowed to enjoy all benefits, including project allowance (an additional amount equal to one-third of monthly salary) and luxury SUVs because most of them hold important positions in the powerful CEB engineers’ union.They claim that the CEB management never holds to account any project manager responsible for long delays, but they are allowed to continue to enjoy all the perks. According to a senior engineer who works as a consultant on project-related work, this guarantee of “job security” acts as a strong incentive for the project engineers to prolong their projects.CEB employees believe another reason for this lackadaisical attitude of CEB top management is that foreign-funded projects have long been a steady source of luxury vehicles for CEB engineers.
Most vehicles used by top CEB engineers including the General Manager have been provided under different foreign-funded projects, as the existing government guidelines will not allow the purchase of such high-end SUVs having large engine capacity including premium European makes like Audi and Mercedes Benz for government officials.CEB employees complain that the Ministry of Power & Energy generally turns a blind eye to these irregularities mainly because the majority of project managers and their project engineers are top officials of the powerful engineers’ union.
They allege that even the Public Utilities Commission of Sri Lanka (PUCSL,) which has the legal obligation to ensure CEB will not make unnecessary or wasteful investments in its transmission infrastructure, has never questioned CEB regarding assets that are idling for many years after spending billions of rupees of public money.
News
Navy seizes an Indian fishing trawler poaching in Sri Lankan waters north of Talaimannar
During an operation conducted in the wee hours of Tuesday (23 Dec 25), the Sri Lanka Navy seized an Indian fishing trawler and apprehended 12 Indian fishermen, while they were poaching in Sri Lankan waters north of Talaimannar.
Recognizing the detrimental effects of poaching on marine resources and the livelihoods of local fishing communities, the Sri Lanka Navy continues to conduct regular operations as
proactive measures to deter such activities. These efforts underscore the collective robust approach steadfast commitment to safeguarding the nation’s marine ecosystems while ensuring the economic security and wellbeing of its citizens.
The fishing trawler along with the fishermen held in this operation was handed over to the Fisheries Inspector of Mannar for onward legal proceedings.

News
India’s External Affairs Minister meets Sri Lanka PM
India’s External Affairs Minister, Dr. Subramaniam Jaishankar, met with the Prime Minister of Sri Lanka, Dr. Harini Amarasuriya, on 23 December at Temple Trees, during his visit to Sri Lanka as the Special Envoy of Indian Prime Minister Shri Narendra Modi.
The meeting took place as part of the official visit aimed at holding discussions with Sri Lanka’s top leadership, at a time when the nation commenced reconstruction efforts following the devastation caused by Cyclone Ditwah.
During the discussions, the Minister of External Affairs of India reaffirmed readiness to extend support for Sri Lanka, including assistance in rebuilding railways, bridges, and strengthening of the agricultural sector in the country. He also highlighted the importance of having effective systems in place to respond to disaster situations, supported by strong legislative, administrative, and institutional frameworks. Both sides reviewed ongoing relief efforts and explored avenues to further strengthen bilateral cooperation in disaster response and recovery.
The Prime Minister commended the Government of India for the continued support, noting that the recovery process following the devastation caused by Cyclone Ditwah include beyond immediate relief efforts to long-term measures such as resettlement, and reconstruction of habilitation and infrastructure.
The Prime Minister further stated that steps have been taken to reopen schools as part of the process of restoring normalcy, with close monitoring in place. The Prime Minister emphasized the need to ensure stability, reduce vulnerability, and strengthen protection mechanisms highlighting the solidarity of the people, their strong spirit of volunteerism, and collective action demonstrated during the emergency situation.
The event was attended by the High Commissioner of India Santosh Jha, Additional Secretary (IOR), MEA Puneet Agrawal, Joint Secretary (EAMO), MEA Sandeep Kumar Bayyapu, Deputy High Commissioner Dr. Satyanjal Pandey, and representing Sri Lankan delegation, Secretary to the Prime Minister Pradeep Saputhanthri, Additional Secretary to the Prime minister Ms.Sagarika Bogahawatta, Director General (South Asia), Ministry of Foreign Affairs Samantha Pathirana, Deputy Director, South Asia Division, Ministry of Foreign Affairs Ms.Diana Perera.
[Prime minister’s media division]
News
Sri Lanka’s coastline faces unfolding catastrophe: Expert
Sri Lanka is standing on the edge of a coastal catastrophe, with the nation’s lifeline rapidly eroding under the combined assault of climate change, reckless development and weak compliance, Director General of the Department of Coast Conservation and Coastal Resource Management (DCC&CRM) Dr. Terney Pradeep Kumara has warned.
“This is no longer an environmental warning we can afford to ignore. The crisis is already unfolding before our eyes,” Dr. Kumara told The Island, cautioning that the degradation of Sri Lanka’s 1,620-kilometre coastline has reached a point where delayed action could trigger irreversible damage to ecosystems, livelihoods and national security.
He said accelerating coastal erosion, rising sea levels, saltwater intrusion and the collapse of natural barriers, such as coral reefs and mangroves, are placing entire coastal communities at risk. “When mangroves disappear and reefs are destroyed, villages lose their first line of defence. What follows are floods, loss of homes, declining fisheries and forced displacement,” he said.
Dr. Kumara stressed that the coastline is not merely a development frontier but the backbone of Sri Lanka’s economy and cultural identity. “More than half of our tourism assets, fisheries and key infrastructure are concentrated along the coast.
If the coast fails, the economy will feel the shock immediately,” he warned.
Condemning unregulated construction, illegal sand mining and environmentally blind infrastructure projects, he said short-term economic interests are pushing the coastline towards collapse. “We cannot keep fixing one eroding beach while creating three new erosion sites elsewhere. That is not management—it is destruction,” he said, calling for science-driven, ecosystem-based solutions instead of politically convenient quick fixes.
The Director General said the Department is intensifying enforcement and shifting towards integrated coastal zone management, but warned that laws alone will not save the coast. “This is a shared responsibility. Policymakers, developers, local authorities and the public must understand that every illegal structure, every destroyed mangrove, weakens the island’s natural shield,” he added.
With climate change intensifying storms and sea surges, Dr. Kumara warned that Sri Lanka’s vulnerability will only worsen without urgent, coordinated national action. “The sea has shaped this nation’s history and protected it for centuries. If we fail to protect the coast today, we will be remembered as the generation that allowed the island itself to be slowly eaten away,” he went on to say.
By Ifham Nizam
-
News2 days agoMembers of Lankan Community in Washington D.C. donates to ‘Rebuilding Sri Lanka’ Flood Relief Fund
-
News7 days agoPope fires broadside: ‘The Holy See won’t be a silent bystander to the grave disparities, injustices, and fundamental human rights violations’
-
News7 days agoPakistan hands over 200 tonnes of humanitarian aid to Lanka
-
Business6 days agoUnlocking Sri Lanka’s hidden wealth: A $2 billion mineral opportunity awaits
-
News6 days agoArmy engineers set up new Nayaru emergency bridge
-
News7 days agoOfficials of NMRA, SPC, and Health Minister under pressure to resign as drug safety concerns mount
-
News7 days agoExpert: Lanka destroying its own food security by depending on imported seeds, chemical-intensive agriculture
-
Editorial7 days agoFlawed drug regulation endangers lives
