Connect with us

News

Wide ranging rackets benefiting CEB engineers

Published

on

By Ifham Nizam

The Ceylon Electricity Board implements most of its power transmission and distribution infrastructure development projects like the construction of new transmission lines, transmission and distribution substations, etc., using loan funds obtained from international lending agencies such as the Asian Development Bank (ADB) and Japan International Cooperation Agency (JICA).

These “concessionary” loans are guaranteed by the government, and projects funded by those loan packages are implemented through specially set up project management units (PMUs).

Engineers attached to PMUs are given special facilities and monetary incentives on the understanding that they will work outside normal working hours and weekends to complete their projects on time and within the allocated budget.CEB often justifies these projects for priority financing citing “great national importance” and the critical needs to improve the power transmission and distribution infrastructure of the country.

Almost all of these project titles carry the words like “green energy”, “clean energy”, “green power”, etc., signifying these investments are primarily aimed at using renewable energy.

However, according to a senior official of the Ministry of Power & Energy, these projects are seldom completed within the given time period or budget. Because of this reason not only the expected benefits of these investments are often lost to the country, but the government incurs heavy losses by way of commitment fees paid to lending agencies.

Once project funds are committed through a loan agreement, the government has to pay this fee to the lending agency, generally computed as a percentage of the loan amount or the “commitment amount”. It is a significant burden to the government, especially in a situation where there is a severe shortage of foreign currency.

If the loan funds are disbursed within the original term of the loan, this “front end fee” is charged at a lower percentage. Hence, when CEB does not complete projects in time, the government ends up paying a higher commitment fee, and is also forced to seek an extension to the original loan disbursement period, thus incurring further costs.

Even more disturbing than long delays in project completion is that some completed projects have turned out to be wasteful investments of foreign funds given to the country.It is understood that the former CEB Chairman M. M. C. Ferdinando had questioned why the new 132kV transmission line between Ambalangoda and Galle, which was completed in 2017 at a cost of Rs. 1,500 million, remained unserviceable to date.

The Sunday Island understands that CEB’s System Control Center is able to switch on this transmission line only when the Samanalawewa Hydropower Plant is running at full capacity.This project had been billed by CEB’s transmission planners as a high-priority investment and solution for the serious transmission bottlenecks in the southern network of the country. Southern areas had been experiencing serious transmission capacity restrictions for decades.It is understood that the CEB General Manager has responded to the Chairman’s inquiry by stating that the commissioning of several new transmission lines that are presently under construction would make the Ambalangoda-Galle transmission line operational.

The 220kV transmission line from Pannipitiya to Polpitiya via Padukka is another example of a costly planning blunder by the CEB. Construction of this long transmission line commenced in 2015 but was delayed owing to many problems, including public protests and court cases filed by some landowners.However, when this ADB-funded project was eventually completed in late 2021 (after a delay of over five years), it has been discovered the power flows in the wrong direction when the line is switched on, causing overloading of the Pannipitiya substation.Hence, this transmission line also remains idle presently. It is understood that CEB planners have explained that power would flow in the right direction once several other transmission lines (being constructed under different loan packages, and already delayed by many years) are completed.

The then CEB General Manager taking part in a national television discussion following the countrywide power outage on August 17, 2020, explained that the unavailability of this critical transmission line was a major contributing factor to CEB’s inability to restore supply for many hours.Another example of colossal waste of funds is the transmission substation at Kappalthurai in the eastern province that has cost the country over Rs. 2,500 million of ADB loan funds. Since there is no high demand for electricity or no future growth in demand in the area, this installation will be idle for the foreseeable future.

According to CEB employees, the existing Trincomalee substation, which is situated about 11 km from this new substation, has ample capacity to serve the electricity demand in the area for many years to come. In the meantime, CEB has made a large investment in increasing the capacity of the Trincomalee substation as well.It is also understood that CEB’s Projects Division has been maintaining several non-functional PMUs for years, spending large sums of money on rented project offices and large project staff, even when no funding has been secured for relevant projects.

CEB employees complain that project directors and their engineers attached to these “white elephants” are allowed to enjoy all benefits, including project allowance (an additional amount equal to one-third of monthly salary) and luxury SUVs because most of them hold important positions in the powerful CEB engineers’ union.They claim that the CEB management never holds to account any project manager responsible for long delays, but they are allowed to continue to enjoy all the perks. According to a senior engineer who works as a consultant on project-related work, this guarantee of “job security” acts as a strong incentive for the project engineers to prolong their projects.CEB employees believe another reason for this lackadaisical attitude of CEB top management is that foreign-funded projects have long been a steady source of luxury vehicles for CEB engineers.

Most vehicles used by top CEB engineers including the General Manager have been provided under different foreign-funded projects, as the existing government guidelines will not allow the purchase of such high-end SUVs having large engine capacity including premium European makes like Audi and Mercedes Benz for government officials.CEB employees complain that the Ministry of Power & Energy generally turns a blind eye to these irregularities mainly because the majority of project managers and their project engineers are top officials of the powerful engineers’ union.

They allege that even the Public Utilities Commission of Sri Lanka (PUCSL,) which has the legal obligation to ensure CEB will not make unnecessary or wasteful investments in its transmission infrastructure, has never questioned CEB regarding assets that are idling for many years after spending billions of rupees of public money.



Latest News

The Sun is directly overhead Warakapola, Aranayaka, Gampola, Bibile, Inginiyagala, and Akkaraipattu at about 12:12 noon today (08)

Published

on

By

On the apparent northward relative motion of the sun, it is going to be directly over the latitudes of Sri Lanka from the  05th to 15th of April this year.

The nearest areas of Sri Lanka over which the sun is overhead today (08th) are Warakapola, Aranayaka, Gampola, Bibile, Inginiyagala, and Akkaraipattu at about 12:12 noon.

Continue Reading

News

AKD admits import of substandard coal, blames technicalities and supplier

Published

on

President

… announces temporary relief package

President Anura Kumara Dissanayake yesterday acknowledged in Parliament that the import of substandard coal had adversely impacted electricity generation.

“There’s an issue with the coal. That’s true,” the President said, addressing the House.

President Dissanayake maintained that the problem had not arisen from the tender process but from the failure of the supplier to deliver coal that met the required standards. “The issue did not arise from the tender process. It resulted from the supplier’s failure to deliver coal that met the required standards. I would also like to point out that coal is not tested by individuals through simple inspection or personal judgment; it is examined in certified laboratories,” he said.

The President went on to say that coal shipments are tested through certified laboratories before dispatch, and an initial payment of 80 percent was made after receiving laboratory certification confirming that the coal meets stipulated specifications.

The President said the balance 20 percent was released only after a second verification carried out by an Indian laboratory selected for the purpose in 2023. Tests had revealed that three shipments failed to meet the required specifications.

The President added that although some shipments had passed laboratory tests, operational assessments at the power plant indicated that the coal was not performing to the expected standard. As a result, the government had withheld the remaining payments for certain consignments, imposed penalties on some suppliers, and in a few instances suspended even the initial 80 percent payment.

He said the use of substandard coal would increase electricity generation costs as the shortfall would have to be compensated by alternative sources, such as diesel. However, he assured Parliament that the additional costs would be recovered from the coal suppliers and would not be passed on to consumers.

The President also said the government expected to receive the fourth and fifth tranches of financial assistance from the International Monetary Fund by the end of May. He told Parliament that Sri Lanka hoped to reach a staff-level agreement with the IMF by Thursday, which would enable the country to secure about USD 700 million in funding.

Meanwhile, the President announced a temporary increase in cash assistance under the Aswesuma welfare programme to provide relief to low-income households during the April festive season.

He said the government continued to face challenges in accurately identifying eligible beneficiaries but noted that Aswesuma remained the only available framework to determine eligibility. Under the scheme, current benefit categories include payments of Rs. 17,500, Rs. 10,000 and Rs. 5,000.

For April, the Rs. 17,500 allowance will be increased by Rs. 7,500 to Rs. 25,000, while the Rs. 10,000 payment will rise by Rs. 5,000 to Rs. 15,000. Beneficiaries in the transitional category will receive an additional Rs. 2,500. The temporary increases are expected to cost the Treasury about Rs. 8.5 billion and will apply only for the month of April.

Addressing electricity tariffs, the President said the adjustment that came into effect on April 1 had been determined earlier and was not linked to the present crisis. According to him, the increase for households consuming less than 30 units amounts to about Rs. 15 per month, while other tier increases translate to approximately Rs. 1 to Rs. 1.50 per day.

He said the government had considered three options to manage rising electricity costs: requiring the Ceylon Electricity Board to absorb the losses, transferring the burden entirely to the Treasury, or passing the cost on to consumers. Instead, the government opted for a shared approach involving the State, the public and the national power system operator.

Under this arrangement, consumers using less than 90 units of electricity will receive a subsidy during the next tariff revision. The government has allocated Rs. 5 billion per month for the programme, amounting to Rs. 15 billion over three months. The President said losses in the electricity sector during the same period were estimated at about Rs. 32 billion.

Turning to agriculture, the President outlined measures to stabilise fertiliser supply amid rising global prices. He said the Department of Agriculture currently held about 14,000 metric tonnes of urea imported at the previous price, while private companies also possessed stocks.

Following discussions with fertiliser suppliers, companies had agreed to release all remaining stocks purchased at the old price to Agrarian Service Centres. These quantities, together with government stocks, are expected to be sufficient for two paddy cultivation seasons.

However, fertiliser required for the third season would have to be imported at higher prices. The President said recent offers for urea ranged from USD 680 to USD 850 per metric tonne.

To cushion farmers from price increases, the government has decided to sell fertiliser for the third season at a fixed price of Rs. 10,200 per bag despite the estimated market price ranging between Rs. 13,500 and Rs. 14,000. The Treasury will absorb the difference, amounting to roughly Rs. 3,000 per bag, at a total estimated cost of about Rs. 1.7 billion.

The President also announced increases in fertiliser subsidies. Farmers cultivating paddy will receive Rs. 30,000 per hectare, up from Rs. 25,000, while subsidies for subsidiary crops during the Yala season will increase from Rs. 15,000 to Rs. 18,000. Small tea holders will receive a one-time additional payment of Rs. 5,000 per fertiliser bag in addition to the existing Rs. 4,000 subsidy.

He said the expanded fertiliser support programme would cost the government about Rs. 6.5 billion, with an additional Rs. 600 million allocated specifically for fertiliser subsidies.

The President also outlined plans to manage rising energy costs, particularly in the fuel sector. He said the government had considered allowing fuel prices to fully reflect market costs or introducing a subsidy mechanism.

According to current estimates, he said, diesel would exceed Rs. 600 per litre if sold strictly at cost. Instead, the government has decided to maintain the existing tax structure and provide Treasury-funded subsidies.

Under the proposed scheme, diesel will receive a subsidy of up to Rs. 100 per litre, while petrol will receive up to Rs. 20 per litre. Fuel prices will continue to be adjusted based on monthly cost calculations, with the next revision scheduled for May 1.

The subsidy programme is expected to cost around Rs. 20 billion per month and will operate for three months at an estimated total cost of Rs. 60 billion.

In addition, fishermen will receive targeted assistance. Small fishing boats will qualify for an extra Rs. 50 per litre fuel subsidy for up to 625 litres per month, credited directly to bank accounts. This will provide a monthly benefit of Rs. 31,250 per boat.

Multi-day fishing vessels will receive a fuel allowance of Rs. 150,000 per vessel during the three-month subsidy period, the President said.

By Saman Indrajith

Continue Reading

News

‘Sri Lanka – China relations: Community with a Shared Future’ launched

Published

on

Chinese and Sri Lankan officials at the book launch

The Chinese Embassy in Colombo launched the commemorative publication in connection with the 70 years of Sri Lanka Diplomatic Relations with China titled, “Sri Lanka – China Relations: Community with a Shared Future” on 03 April 2026 in the presence of a large distinguished audience.

Cao Jing, Deputy Director General of the Asian Department of the Ministry of Foreign Affairs, Officials of the Chinese Foreign Ministry, Diplomatic Corps, Xu Yan of the Chinese People’s Association for Friendship with Foreign Countries, officials of Ministry’s line agencies and state-owned enterprises and several other guests having interests in Sri Lanka participated at the event.

The commemorative publication captures the essence of Sri Lanka’s resilience as a nation by tracing its rich history, civilization and culture. It offers insights into salient features of Sri Lanka that has been recognized for ages as “a land like no other”.

The publication was authored by the distinguished career Ambassador Dr. Ananda Kumarasiri.

In delivering the opening remarks Ambassador Majintha Jayesinghe, expressed his appreciation to the author Dr. Ananda Kumarasiri. Recalling the establishment of Diplomatic Relations in 1957, Sri Lankan Ambassador stated that the impressive tapestry of genuine friendship that exists between our two countries since ancient times have grown exponentially.

Ambassador Majintha Jayesinghe expressed the aspiration that this book will present an insightful account of the rich heritage of Sri Lanka’s relations with China. He hoped that the commemorative publications would encourage future generations to look at the shared history and relations with pride and motivate them to further enhance this unique friendship and goodwill to higher vistas of achievements.

In his address, Ambassador, Dr. Ananda Kumarasiri among other important observations, pointed out that there is much scope for Sri Lanka and China to collaborate in a number of fields. In particular, he highlighted that China’s tremendous technological and industrial progress can be harnessed for Sri Lanka to embark into-the development of alternative sources of energy, backward integration of Sri Lanka’s primary resources that would ensure value added exports and also in recycling wastes from various primary resources.

Continue Reading

Trending