Four Irrigation Department projects started 14 years ago still not completed

Published

on

Only Uma Oya Diversion to be completed this year

By Lalith Chaminda and S.K. Kaluarachchi

Four projects that the Irrigation Department commenced 14 years ago, at a cost of Rs. 90 billion had not yet been completed, the National Audit Office (NAO) said. The NAO said that the department had taken twice the time originally scheduled for these projects.

These are Thalpitigala tank, productivity promotion and irrigation scheme efficiency management system, Gin Nilwala Diversion Project and Uma Oya Diversion Project. The estimated costs of these projects now stand at Rs 153 billion. Although almost 60 percent of the allocated money had been spent, none of the projects were near completion, the report has said.

The NAO has proposed that the Irrigation Department analyse the impact of the delays on the expected benefits and this report must be presented to the cabinet of ministers.

The NAO has also said that some staff have been recruited on contract basis and that there have been delays in giving them service extensions. This too has caused disruptions, the NAO says. It recommends that the Irrigation Department audit the work so far and estimate the future costs and benefits of the projects.

In response, the Head of the Irrigation Department said that 90 percent of the Thalpitigala Tank project had been completed. However, the productivity promotion and irrigation scheme efficiency management system could not achieve the expected results because the department didn’t get the promised funding from the treasury.

“The Gin-Nilwala Diversion Project has been delayed because of a number of economic, social and political factors. However, the Uma Oya Diversion Project will be completed by the end of 2022,” he said.



Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest News

IMF Executive Board approves US$206 Million in Emergency Financial Support for Sri Lanka

Published

on

By

The IMF Executive Board approved emergency financing under the Rapid Financing Instrument (RFI),  providing Sri Lanka with immediate access to SDR 150.5 million (about US$206 million,
equivalent to 26 percent of quota) to help Sri Lanka address the urgent needs arising from the catastrophic Cyclone Ditwah and preserve macroeconomic stability.

 

Continue Reading

Latest News

Navy clears major bridge obstructions in Peradeniya and Lewella

Published

on

By

In response to severe weather impacts, the Sri Lanka Navy conducted a diving and technical assistance operation on Friday (19 Dec 25) to clear major debris obstructing vital infrastructure.

Heavy rainfall caused a significant rise in the water level of the Mahaweli River, washed  large quantities of debris, including logs and bamboo, downstream. These  remain lodged in the Diyakapanathota in Gatambe, Peradeniya and Lewella bridges, obstructing the smooth flow of water.

Acting promptly upon request, a Navy diving team executed a coordinated operation in collaboration with the Road Development Authority. The team removed the accumulated debris, restoring normal water flow through the bridges.

 

Continue Reading

Latest News

Landslide early warnings issued to the districts of Badulla, Kandy, Kurunegala, Matale and Nuwara-Eliya extended till 8AM on Sunday (21)

Published

on

By

The Landslide Early Warning Centre of the National Building Research Organization (NBRO) has extended the Landslide Early Warning issued to the districts of Badulla,  Kandy,  Kurunegala,  Matale and Nuwara-Eliya till  08:00AM on Sunday (21st December 2025)

The LEVEL III RED landslide early warnings issued to the Divisional Secetaries Divisions and surrounding areas of Medadumbara, Doluwa, Ududumbara and Minipe in the Kandy district,  and Nildandahinna, Hanguranketha, Mathurata and
Walapane have been extended.

LEVEL II AMBER   landslide early warnings have also been issued to the Divisional Secetaries Divisions  and surrounding areas of Soranathota, Hali_Ela, Passara,  Meegahakivula, Badulla, Lunugala and  Kandeketiya in the Badulla district,  Thumpane, Harispattuwa, Udapalatha, Kundasale, Akurana, Poojapitiya, Udunuwara, Pathadumbara, Pasbage Korale, Gangawata Korale, Hatharaliyadda, Yatinuwara, Ganga Ihala Korale, Panvila, Pathahewaheta and Deltota in the Kandy district,  Rideegama in the Kurunegala district,  Ukuwela, Naula, Matale, Ambanganga Korale, Rattota, Pallepola, Wilgamuwa, Yatawatta and Laggala Pallegama in the Matale district,  and Nuwara-Eliya in the Nuwara-Eliya district.

LEVEL I YELLOW landslide early warnings have been issued to the Divisional Secetaries Divisions and surrounding areas of  Uva Paranagama, Welimada, Haputhale, Haldummulla, Ella and
Bandarawela in the Badulla district, Alawwa, Mallawapitiya,
Polgahawela and Mawathagama in the Kurunegala district,  and Kothmale East, Ambagamuwa Korale, Kothmale West, Thalawakele and Norwood in the Nuwara-Eliya district.

 

Continue Reading

Trending