Ceylon Energy and HJT China complete key SESRIP power distribution milestones

Published

on

Ceylon Energy, in collaboration with HJT China, has successfully completed the Mahiyangana and Kappalthurei 33kV power distribution lines, alongside the Uhana Gantry, a key component of the Supporting Electricity Supply Reliability Improvement Project (SESRIP). SESRIP aims to enhance energy access in underserved regions of Sri Lanka, covering 2,372 kilometers of low-voltage lines and 106 rural electrification schemes. The project will provide reliable electricity to over 35,000 households, particularly in the Northern, Eastern, Uva, and North Central provinces. With a total investment of USD 42 million funded by the Asian Development Bank, SESRIP also focuses on integrating renewable energy sources, improving electricity reliability, and supporting sustainability goals.