Features
Power sector reforms- urgent need to revisit them
by Dr Janaka Ratnasiri
The government of Sri Lanka (GoSL), in a policy decision made in 1998, expressed its commitment to power sector reforms and embarked on a programme to restructure it by unbundling the Ceylon Electricity Board (CEB) into separate companies for generation, transmission, and distribution, as reported in the ADB Report on Country Assistance Programme Evaluation: Power Sector Assistance Evaluation, August 2007. To give effect to this policy, a Bill was drafted to introduce reforms in the power sector as far back as 2002.
ELECTRICITY REFORMS ACT 28 OF 2002
The draft titled Electricity Reforms Bill was presented to the Parliament in 2002, outlining sector reforms comprising restructuring of the electricity industry by breaking the Ceylon Electricity Board (CEB) and Lanka Electricity Company (LECO) into several independent state-owned companies to carry out generation, transmission, and distribution functions.
The Bill proposed that independent companies be incorporated for the following purposes:
One company to take over the functions of the CEB relating to hydroelectricity generation and thermal electricity generation,
One company to take over the functions of the CEB relating to transmission and bulk procurement of electricity,
Three or more companies to take over the distribution of electricity, and
One or more companies to take over other functions of the CEB and LECO.
The Bill when presented to the Parliament brought in strong protests from many quarters including the CEB trade unions and other trade unions as well as from several political parties. They saw this Bill as an initial step towards privatizing the CEB and consequently loss of employment for its staff. Once the government gave the workers an assurance that the workers’ rights would be safeguarded, the protests died down and the Bill was passed in March 2002. It was gazetted as Electricity Reforms Act No. 28 of 2002 on 13 December 2002. However, the necessary order to give effect to the Act was not gazetted by the Minister and as a result the Act did not come into operation.
ENERGY EXPERT’S RECOMMENDATIONS FOR UNBUNDLING THE POWER SETOR
Prof. Priyantha Wijayatunga, Director of the South Asia Energy Division of Asian Development Bank (ADB) said at the launching of the Techno 2019 exhibition held in July 2019, that “Sri Lanka still needs to go a long way in relation to sector governance, compared to other countries in the region. It is time that we look at this closely so that we do not lag behind. Reforms will undoubtedly help the energy sector and hence the country’s economic development,” (Daily Mirror, 18.07.2019).
He specifically pointed out that improved governance in the energy sector in India and Bangladesh enormously helped conceptualizing and implementing clean energy initiatives, while enhancing their energy security. He highlighted the important role played by independent energy regulators and separation of functions of the energy sector in these countries, which had paved the way for breakthroughs in clean energy initiatives.
Prof. Wijayatunga elaborated “By now, a large majority of the countries, including many in the developing world around us, have fully unbundled the energy supply industry with a reasonably independent regulatory environment. If we look at South Asia, India and Bangladesh have already significantly advanced and are rapidly progressing in these areas,”. Further, he noted that “reforms also led to an increase in private sector participation in all sub sectors, including generation, distribution and even in transmission business in these countries”.
RECOMMENDATIONS OF INTERNATIONAL ORGANIZATIONS
The GoSL, from time to time, engaged the services of international institutions such as World Bank (WB), Asian Development Bank (ADB) and Japan International Cooperation Agency (JICA) to make recommendations to improve the power sector. Among the reports produced from these studies are:
JICA Master Plan Study on the Development of Power Generation and Transmission System in Sri Lanka, February 2006,
Asian Development Bank report on Assessment of Power Sector Reforms in Sri Lanka, 2015,
JICA Report on Electricity Sector Master Plan Study in Sri Lanka, March, 2018, and
World Bank Group study on Sri Lanka Energy Infrastructure Sector Assessment Programme (InfraSAP), April 2019.
The 2006 JICA report observed that “political intervention is making it impossible for the CEB to manage itself autonomously. As a result, its management has been criticized as inefficient by external parties. Moreover, it has piled up a debt big enough to jeopardize its continued sustenance. One of the areas where politics has been heavily involved is the tariff question. Thus far, political considerations have worked against attempts to raise tariffs, and tariff revisions to reflect the costs have consequently been delayed. To put a halt to political intervention in CEB management as well, it is necessary to lay down the proper conditions for corporate business. This is to be done by unbundling the current CEB, which is a vertically integrated government-owned monopoly; making the generation, transmission, and distribution divisions completely independent”. The report further recommended that “a fundamental reform of the sector is absolutely essential for promotion of long-term investment and increase in the overall efficiency. To this end, the government must present a detailed vision and schedule for CEB unbundling, and swiftly complete the reform, which is currently stalled.” But no follow up action was taken by the GoSL towards unbundling of the CEB.
The 2015 ADB report in its concluding paragraph said that “The next stage of reform requires establishing six independent companies out of the CEB’s generation, transmission, and four distribution licensees. The organization culture in the government-owned company LECO needs to be replicated in the CEB’s distribution licensees by creating corporate entities that report to the CEB holding company. The functional business units currently established within the CEB are adequately staffed and organized to enable the formation of six corporate entities. The corporatization need not involve privatization if political decision makers do not wish to involve private capital more fully in the sector, provided the state-owned firms operate as independent commercial companies”.
The ADB report further said that “The electricity sector was proposed to be restructured to ensure increased efficiency, transparency, autonomy, accountability, competition, and financial viability. The CEB functions were to be vertically and horizontally unbundled. For this purpose, the CEB owned subsidiary companies were planned to be established under the Companies Act No. 17 of 1982. The electricity sector was proposed to be restructured to ensure increased efficiency, transparency, autonomy, accountability, competition, and financial viability. The CEB functions were to be vertically and horizontally unbundled. For this purpose, CEB owned subsidiary companies were planned to be established under the Companies Act No. 17 of 1982”.
The 2018 JICA report reviewed and updated the 2006 JICA Master Plan. However, it did not refer to the issue of unbundling the power sector but recommended incorporation of renewable energy projects as well as natural gas in the energy mix for generation of electricity up to 2040 including consideration of financial commitments. It also considered the option of generation with 100% renewable energy sources by 2040, recommending that to meet the deficit of power arising out of continuing high cloud cover for several days, storage batteries need to be installed at an estimated cost of USD 1,000 million.
The 2019 World Bank report says “Apart from a few recent competitive outcomes, the country has not yet been able to develop utility scale non-conventional renewable energy (NCRE) projects at tariffs comparable with other projects globally or in the region or to tap into commercial financing and private sector participation in larger scale projects. As part of the preparation of the InfraSAP, two pre-feasibility assessments for potential large scale NCRE park sites were conducted for sites in Pooneryn and Moneragala, respectively, totaling about 500 MW of potential generation capacity”.
“The Solar and Wind power has the potential to further optimize the cost of power in the country. In line with what is being witnessed across the globe (i.e. low tariffs in solar and wind-based generation), it seems reasonable to assume that by opening the sector to international players with adequate incentives and risk mitigation mechanisms in place, a significant reduction in cost of power could be achieved in Sri Lanka. The solar and wind-based generation could be potentially used to replace some of the expensive imported oil-based power, which is currently utilized to offset the low availability of hydro resources” (p. 17).
Though the government sought the assistance from these multilateral agencies for improving the performance of the CEB, it has not taken any initiative to implement them, particularly those on reforms. The CEB is also rather slow in pursuing building of large-scale solar energy systems despite the government giving high priority for them and availability of funding from India on a credit line to the extent of USD 100 million specifically for solar energy project development (See The Island of 03.09.2020)
PRE-REQUISITES FOR UNBUNDLING OF CEB
Once the CEB is unbundled, separate companies are to be set up to take over the generation, transmission, distribution and other functions. There will be one company each for generation and transmission and three or more for distribution, according to the draft Act. However, it will be more prudent to have separate generation companies for each of the generation complexes, Kelanitissa, Laxapana, Mahaweli and others including large renewable energy plants. These companies will serve as independent power producers (IPP) and will have to sell the energy they generate to the transmission company, along with other IPPs. Electricity generated at power plants other than from small power plants, is transmitted to grid substations using 220 kV and 132 kV transmission lines.
When the available capacity exceeds the demand, the System Controller will have to decide the amount of power to be purchased from the IPPs based on a merit order system. Generally, plants providing firm output at low cost is given priority according to which power from renewable sources may get low priority. However, with the government policy to meet a minimum of 80% of generation from renewable sources, a mechanism will have to be worked out to accept power from RE sources, possibly by providing storage facilities which will even out their fluctuations.
Before selling energy, it has to be measured to an accuracy of at least ±0.1% using instrumentation which need to be type approved by the Department of Measurement Units, Standards and Services (MUSS) as required by the relevant law. Further, the instruments need to be regularly calibrated by an accredited laboratory. The CEB is already having a Meter Laboratory and this may have to be brought under the control of the transmission company with updated instrumentation serving as secondary standards with accuracy traceable to international standards. This can be verified by calibrating them against the primary standards available at MUSS Department, which is a legal requirement. Every generating unit before being connected to the grid for transmission, needs to go through the metering unit which will monitor the energy dispatched on a daily or monthly basis and transmit the data to the transmission company. It will then pay the IPP at rates agreed to in the power purchase agreement entered into between the IPP and the transmission company, based on the energy dispatched.
For distribution, the CEB has already divided the country into four regional divisions and a subsidiary company, Lanka Electric Company Ltd, covering the Western coastal townships from Negombo to Galle, excluding the city of Colombo. Electricity distribution from 220 kV/132 kV grid substations to the rest of the country is carried out using 33 kV lines which are again converted to 11 kV at load centres for local distribution. The 33 kV or 11 kV line voltage is again converted into 230/400 V for supplying to consumers. Currently, one 33 kV line may extend across two division boundaries, but if these two divisions are to be set up as two independent companies, there has to be separate distribution lines, each covering only one division receiving electricity from one or more GSSs located within the division. It will be then possible to measure the amount of energy transferred to this particular distribution company separately. Hence, certain amount or modifying the distribution system may have to be undertaken prior to unbundling.
FINANCIAL VIABILITY OF CEB
The CEB has been selling electricity to most of its consumers below cost price which is around Rs 20 per unit. For example, the tariff for households consuming up to 90 kWh per month is only Rs. 10 per unit for the last 30 units and less for lower slabs. For industries with demand up to 42 kVA and for other industries during daytime, the tariff is below the cost price. The average cost of generation per unit of electricity in 2017 was Rs 20.40, while the average selling price per unit in 2017 was Rs. 16.26. The corresponding values for 2018 were Rs. 19.12 and Rs. 16.29, respectively. These low tariffs resulted in the CEB incurring a net loss of Rs. 47.6 billion in 2017 and Rs. 30.5 billion in 2018 (AR, 2018).
In view of these losses, the CEB has not been able to settle its dues to the Ceylon Petroleum Corporation (CPC) for supplying fuel in 2016 amounting to Rs. 12.43 billion and also to settle the payments to IPPs for supplying power which amounted to Rs. 21.52 billion in 2016, according to General Manager’s Review appearing in the 2016 Annual Report (AR). Further, the total long-term borrowings as at end of 2016 were recorded as Rs. 220.5 billion, while that for 2018 were recorded as Rs. 281.3 billion, as given in respective annual reports. This poor financial status of CEB is an impediment for it to raise any borrowings from commercial banks.
The subsidies given to low-end consumers amounted to Rs. 70 billion in 2017 and Rs. 60 billion in 2018 (AR 2018). These were partly recovered by selling to high-end consumers at above-average cost price. The surplus recovered by these means in 2017 was Rs. 15.2 billion and Rs. 20.6 billion in 2018. Had the CEB was operating as a commercial enterprise, the logical measure that would have been done was either to increase the selling price above the cost price for all consumers and also reduce the cost of generation.
Being a government organization, the tariff is determined by the government policy to provide electricity to low-income households at an affordable price and hence the CEB is constrained against raising the tariff. However, this issue needs to be carefully studied and an upward revision of the tariff should be considered, removing the subsidies at least partly. Even for industries, to make them competitive in the global market, the government policy is to supply electricity to small and medium industries at below cost, but this policy too needs to be reviewed.
There is also the possibility to reduce the cost of generation. The CEB has been generating electricity from petroleum oil to the extent between 25% – 35% with the generation in 2017 being 5,000 GWh. According to 2016 Generation Performance Report of the Public Utilities Commission of Sri Lanka (PUCSL), the cost of generation from oil-fired power plants has been between Rs/kWh 22 and Rs/kWh 38. On the other hand, the cost of generation from NG fired power plant is no more than Rs/kWh 15 as quoted in the tender for the 300 MW gas power plant to be installed at Kerawalapitiya. If the thermal power plants presently operating with diesel are converted to NG, the saving is of the order of Rs. 50 billion annually.
The Cabinet of Ministers as far back as December 2010 decided to introduce natural gas (NG) in all sectors including power and industries and authorized the Ministry of Petroleum to pursue the matter, but no action was taken either by the Ministry of Petroleum or Ministry of Power and Energy. It is hoped that with the mandate given to the Ministry of Renewable Energy to convert all oil power plants at Kelanitissa complex for operation with NG, will inspire the CEB to give priority for this conversion which will reduce the losses incurred by the CEB.
The other matter that needs to be resolved is the delay in public sector organizations not paying up their bills for electricity on time, and this has caused liquidity problems in the CEB. As a result, the CEB is unable to pay the CPC for the fuel it purchases from the CPC on time and also unable to pay the IPPs for the power it purchases from them on time. With the unbundling of the sector, this system could be improved. Every Distribution Company (DC) should collect the payments due from the consumers on time giving a grace period of say one month. The Transmission Company (TC) should collect the payments from every DC for the electricity sold to them on time and settle the payments due for each of the Generation Companies (GC) on time. The GCs could then settle the payments due for each of the IPPs for the electricity they purchase from them. With the availability of on-line banking facilities and smart metering systems, all these operations could be undertaken without human intervention, other than occasional verification.
PRESENT STATUS OF SRI LANKA’S POWER SECTOR
In 1969, the Ceylon Electricity Board (CEB) was established by an Act of Parliament for the purpose of developing and coordinating of generation, supply and distribution of electricity island-wide, taking over the functions of the Department of Electrical Undertakings. By the end of 2018, the total installed capacity has grown to 4,045 MW of comprising 1,400 MW of hydropower plants, 1,137 MW of oil power plants, 900 MW of coal power plants and 608 MW of other renewal energy plants owned by both CEB and independent power producers. The total electricity generation in 2018 was 15,300 GWh, with the per capita electricity consumption 650 kWh, which is only above the least developed countries in Asia. The forecast for generation in 2030 given in CEB’s long term generation plan is around 31,000 GWh.
In 1983, Lanka Electric Company was established as a subsidiary company of the CEB and took over the distribution of electricity in coastal townships between Negombo and Galle, which resulted in reducing the distribution losses. In 2007, the Sri Lanka Sustainable Energy Authority (SLSEA) was established with the main objective to identify, assess and develop renewable energy resources in the country. However. The SLSEA has been operating more as a regulator than as a promoter of RE projects.
It is noteworthy to compare Sri Lanka’s power sector situation with that of another Asian country, Taiwan, where the population in 2018 (23.78 million) is similar to that of Sri Lanka (21.67 million) and land area (36,200 sq. km) is almost half of Sri Lanka’s (65,610 sq. km). Taiwan’s installed capacity in 2018 was a staggering 44,600 MW comprising 13,000 MW of coal power plants, 16,000 MW of natural gas power plants and 4,500 MW of nuclear power plants, generating 275,500 GWh of electricity in 2018 giving a per capita consumption of 11,585 kWh compared to 650 kWh for Sri Lanka (Wikipedia). The rapid growth of industrialization has been the main driver of the power sector, with a GDP (nominal) per capita of USD 24,800 in 2018 compared to USD 4,100 for Sri Lanka. It will be interesting to find out how Taiwan was able to achieve such high performance in the power sector – whether superior competency and dedication of professionals or correct policies in place or strong political leadership.
LACK OF TRANSPARENCY IN SELECTING MAJOR PROJECTS
Unlike in many Asian countries, Sri Lanka has been able to provide electricity to almost 100% of households, which was made possible through funding made available through decentralized budgeting in which provision of electricity to rural villages has been given priority. While the national grid was extended to cover almost the entire island to meet the power demands of every industry, commercial establishment and household, the CEB has not been able to expand its generation capacity correspondingly.
Efforts to build a coal power plant kept dragging for over 20 years at the beginning of the mid-eighties due to the CEB’s failure to initiate a dialogue with the public and concerned parties and vacillating policies of the government. Instead of inviting bids for building a power plant meeting performance and emission specifications from reputed manufacturers internationally and selecting a plant in a transparent manner, the CEB accepted a plant based on outdated technology offered by China on credit. The plant is known to breakdown repeatedly and the CEB is compelled to retain Chinese technicians even today to attend to its maintenance. Though the CEB claims that the coal power plant generates at the lowest cost, when the cost of financing is added, the cost gets more than doubled as revealed by a study undertaken by World Bank team.
On three occasions between 2000 and 2010, Sri Lanka government announced calls for expressions of interest for building thermal power plants on BOOT basis with capacity 1,000 – 1,200 MW, but pursued none. This gives a poor image of Sri Lanka within the international power industry, as the investors have to incur heavy expenditure on site visits and making bid bonds. In one announcement, the fuel option was kept open to solid or liquid or gas and the site to be selected by the investor while in another, the fuel option was specified as coal with the site to be near Hambantota.
In 2005, India offered to build a 500 MW coal power plant at Sampur, near Trincomalee on cost-sharing basis. Negotiations between the Indian party and the CEB kept dragging for five years before the final agreement was entered into and another five years to get feasibility studies and environment impact studies completed as well as other clearances obtained. By that time, the new government had changed its policy to adopt gas power rather than coal power on environmental grounds and the project was aborted. Had the CEB not taken such a long time to finalize the terms and commenced work sooner, the plant would have been built by now. It needs to be stressed that the proposed coal power plant at Sampur was abandoned because the CEB was dragging the project for nearly 10 years. The project took so long to commence work, obviously because it had problems both technical and operational which the CEB was unable to resolve. Hence, it was best to cancel the project and consider a new project afresh.
The latest attempt to build a 300 MW gas power plant at Kerawalapitiya on BOOT basis also got dragging for nearly four years mainly because of the manner in which the project selection process was handled by the CEB. A 500-page request for proposal (RFP) was announced in November 2016 seeking unnecessary details while the more important information essential for making a decision was left out. Such detailed information would have been in order had CEB was paying for the capital expenditure. With a BOOT project, the investor will ensure that a plant worth the money would have been purchased. The CEB will only have to know the price at which energy be sold to CEB and whether the plant satisfies performance and emission specifications laid down by the CEB.
The lack of clarity in the RFP resulted in the matter taken to the courts for a ruling. Though the approval of the Cabinet has already been granted for the project and the new President has directed this project be given priority soon after he was elected, the CEB has still not finalized its acceptance. Instead, the CEB is pursuing building a 300 MW coal power plant at Norochcholai against President’s policy. Incidentally, China was allowed to build a 400 MW gas power plant along with an LNG terminal at Hambantota with no such detailed RFPs announced.
According to a SLSEA Report dated 27.03.2019, several RE projects submitted by investors that have received the approval of the SLSEA since 2016 have been held up as CEB has not agreed to sign power purchase agreements with them, citing a section of the Electricity Act. This includes 101 RE projects with total installed capacity of 3,052 MW comprising 264 MW of mini-hydro plants, 2,028 MW of solar plants, 673 MW of wind plants and 87 MW of other plants, which could generate over 7000 GWh of energy annually. This situation is shown in Fig. 2 in 2018 Annual Report where the growth of energy added from RE projects to the system shows a stagnation between 2015 and 2018, with the value for 2016 showing a drop of 200 GWh compared to other years. It appears that there was no coordination between the CEB and the SLSEA.
FLAWED LONG TERM GENERATION EXPANSION PLAN
The CEB during the last few decades has been preparing biennially a long-term generation expansion (LTGE) Plan and the mandate of the Power Ministry specifies that the sector should be developed to comply with the CEB Plan. It is supposed to determine which power technology will be the cheapest in 20 years hence based on current prices. With the cost of generation depending on plant capital cost and fuel prices both of which could vary widely within a span of 20 years, it is futile to make forecasts now as to which technology is the cheapest in 20 years hence and to adopt it. Therefore, to give a mandate to follow the CEB’s LTGE Plan which is highly flawed for the development of the sector, does not make sense. The CEB Plan for 2018-2037 recommends adding 2,700 MW of coal power plants between 2023 and 2037 under Base Case scenario saying it is the cheapest option. However, the 2019 World Bank report cited above says in p. 18 that “coal ceases to be the least cost source of power generation, as cost of power from LNG and NCRE could potentially be lower than US cents 9 / kWh” which is the estimated coal power price.
When the CEB submitted its LTGE Plan for 2018-37 to the Public Utilities Commission of Sri Lanka (PUCSL) for approval as required by the Sri Lanka Electricity Act No. 31 of 2013, PUCSL did not approve it but proposed an alternative plan incorporating natural gas power plants in place of coal power plants included in the CEB Plan. The CEB refused to accept this recommendation and the dispute between the PUCSL and the CEB kept dragging for over a year, and the matter was finally referred to the President who gave a directive to the PUCSL to approve the CEB Plan, fearing disruption to the power supply in the country after the CEB Engineers’ Union threatened to resort to industrial action if their demand for coal power plants is not acceded to. This is a clear indication that Sri Lanka’s power sector is being governed not by the PUCSL nor the Ministry nor the Governing Board of the CEB, but by its trade unions. This justifies Prof. Wijayatunga’s statement that “Sri Lanka still needs to go a long way in relation to sector governance”.
CONCLUSION
The CEB ha a staff strength about 23,000 with over 1,400 professionals. It is the opinion of several international agencies that this organization be split into several organizations each responsible for different functions undertaken by the CEB, including generation, transmission and distribution. It is expected that such an unbundling process will improve the efficiency, transparency, autonomy, accountability, competition, and financial viability. The CEB has failed miserably in the recent past to increase the generation capacity to meet the growing demand with due consideration for environmental concerns even after granting Cabinet approval for many of them. It has also failed to initiate work on large renewable energy projects for several years, particularly during the last seven months even after the President’s policy of pursuing renewable energy and gas power projects was announced.
Possibly the high inertia of the CEB with its large staff prevents it from being flexible to undertake new projects in keeping with international trends and hence continues to insist on outdated technologies. Hence, it is desirable if the government initiates unbundling of the CEB urgently as recommended by reputed energy experts to make it more flexible. The unbundling will also give an opportunity for the government to get rid of dead wood after giving them a golden hand shake.
Features
Combining local resources,traditional knowledge and science to build a food-secure Sri Lanka
World Food Day 2026: Innovating today for a better food future
by Dr. Kaushalya Wijayasekara
What will be on the Sri Lankan dinner table ten years from now? Will our children be able to get nutritious food at a price their families can afford? Will farmers be able to grow enough despite changing weather and rising costs? And how much of the food we produce will actually reach the consumer, instead of being lost or wasted along the way?
These questions can’t wait. A farmer faces unpredictable weather. A family faces rising food costs. Fruit goes unsold after a good harvest. Some children do not get enough nutrition. The future of food is tied to the future of Sri Lanka itself.
World Food Day 2026 is a chance to look beyond the immediate problems and ask whether we can build a food system that feeds our people well, gives farmers better opportunities, protects the environment and makes better use of what we already have. The answer can be yes, but we will have to think differently.
We are not starting from zero. Sri Lanka has diverse crops, fisheries, traditional food knowledge, indigenous varieties, research institutions, universities and a young generation able to create new solutions. What we need is to bring these together and act. Producing more will not secure our food future on its own. It will depend on how intelligently we produce, process, preserve, distribute and consume food.
Making more of what we already have
Innovation does not always mean inventing something new. Often it means finding better uses for the resources we have.
Sri Lanka grows traditional rice varieties, kurakkan, green gram, cowpea, jackfruit, breadfruit, cassava, sweet potato, coconut and palmyrah. All of them have great potential for modern, nutritious, value-added foods. Jackfruit and breadfruit can be made into flour and other convenient products. Traditional rice varieties can go into new foods that suit changing consumer needs. Palmyrah, with its strong cultural heritage, can create new income through better processing, packaging, quality assurance and market development.
The aim is to connect our traditional food knowledge with modern consumer needs and technology, while keeping our food heritage.
Stop wasting the food we produce
Reducing food loss and waste should be a major priority. Seasonal fruits such as mango, banana, papaya and pineapple can be lost in large quantities when production exceeds demand or when storage, transport and processing facilities are inadequate. With suitable technology, these fruits can become dried products, pulps, powders, beverages and other shelf-stable foods.
Agricultural and fisheries by-products are resources too. They could be turned into food ingredients, animal feed, bio-based products and other useful materials, which would move us toward a more circular food economy.
Technology alone is not enough. We need stronger local processing facilities, cold storage, efficient transport, collection centres and market information systems, especially close to where food is produced. Cutting food loss raises the value of what our farmers and fishers already produce.
Nutrition and food safety come first
Food security means more than having enough food. People also need food that is safe and nutritious.
Sri Lanka can develop affordable, nutritious foods from local pulses, grains, vegetables, fruits and fish. Children and other vulnerable groups should get particular attention. Schoolchildren in particular deserve a focus: safe, nutritious, locally sourced products for school feeding programs would support child nutrition, local farmers and domestic food industries at the same time.
Food safety must stay at the centre of food innovation. Good hygiene, quality control, laboratory testing, traceability and appropriate food safety systems are what make new products safe as well as attractive and nutritious.
A food system that can cope with climate change
Climate change is already affecting agricultural production, water availability, crop yields and food prices. We need food systems that can handle changing conditions. That means climate-resilient crops, efficient water use, soil and water conservation, better storage and resource-efficient food processing.
Traditional knowledge matters here. Generations of Sri Lankan farmers have developed practices suited to local climates and ecosystems. Combining that experience with modern science can give us solutions that fit local conditions and are sustainable. Technology alone will not build the future of food. Science, experience and local knowledge together can.
Give young people a bigger role
Sri Lanka’s universities have an important part to play in shaping our food future. Young people should be encouraged to identify real problems in the food system and work on practical solutions in areas such as food waste, sustainable packaging, nutrition, food safety, modernising traditional foods and digital technologies.
A good research project should not always end as a research paper. Where appropriate, research should be supported to move on to products, technologies, enterprises and community solutions. That needs stronger partnerships between universities and industry, along with mentoring, research funding, business support and market connections. If young researchers and entrepreneurs can turn their ideas into viable food innovations, both consumers and producers will benefit.
A pathway designed for Sri Lanka
We do not need to copy food-system models from other countries. We can build a pathway that suits our own resources, culture and needs. It would bring together local resources, traditional knowledge, scientific research, appropriate technology and entrepreneurship, with farmers, fishers, universities, research institutions, food industries, entrepreneurs and policymakers working side by side.
The goal goes beyond selling raw materials. We need to create more value, reduce waste, improve nutrition, generate jobs and strengthen rural livelihoods. This matters especially for small and medium-scale food enterprises, which can drive local economic development when they get the right technical, financial and market support.
The choices we make today
The food future will not create itself. It will be shaped by what we grow, what we research, what we process, what we consume and what we choose not to waste.
So, the question for World Food Day 2026 is this: what can we do today so that every Sri Lankan has safe, nutritious, affordable and sustainable food tomorrow?
The answers are already around us, in our farms, fisheries, food businesses, universities, laboratories and communities. We have the resources, the traditional knowledge, the scientific expertise and talented young people. What we need now is to connect them and act.
A better food future begins with the choices we make today.
Dr. Kaushalya Wijayasekara
Senior Lecturer, Department of Biosystems Technology, Faculty of Technology, University of Ruhuna
Features
20th Anniversary of Digampathana blast – the day Sri Lanka Navy cried
By Admiral Ravindra C Wijegunaratne
WV, RWP and Bar, RSP, VSV, USP, NI (M) (Pakistan), ndc, psn, Bsc
(Hons) (War Studies) (Karachi) MPhil (Madras)
Former Navy Commander and Former Chief of Defence Staff
Former Chairman, Trincomalee Petroleum Terminals Ltd
Former Managing Director Ceylon Petroleum Corporation
Former High Commissioner to Pakistan
The Digampathana suicide truck attack on 16th October 2006 remains the deadliest single strike in Sri Lanka Navy history, leaving scars that time cannot erase.
It was a seemingly ordinary Monday morning on 16 October 2006, but the calm of that day would soon be shattered in a way none of us could have imagined. As the Commandant of the Naval and Maritime Academy and Flag Officer Commanding Naval Fleet at Trincomalee, I was aware that a number of my cadets were travelling that morning, part of a convoy of fifteen buses carrying naval personnel from Trincomalee, Colombo, and other bases, heading toward Dambulla to rendezvous with another group. The convoy also included trucks and escort vehicles, a routine movement planned and coordinated with the army to ensure the roads were clear. The morning started quietly. Some personnel greeted friends, handed over their weapons, or strolled to a nearby tea shop. It all seemed so ordinary—too ordinary for what would come next.

Sri Lanka Navy sunk LTTE Ships carrying arms, ammunition and warlike materials thousand miles away from Sri Lanka in Indian Ocean in September and October 2007.
By late morning, both convoys had reached the small ground at Digampathana, near the Sigiriya junction, and personnel mingled briefly, unaware that a carefully orchestrated act of terror was waiting. Then, suddenly, an empty half-truck veered directly into the convoy. It exploded with a ferocity I can still recall as if it were yesterday. Nuts, bolts, and high explosives tore through the air. Pandemonium erupted instantly. I later learned that 107 of our naval personnel were killed on the spot and another 153 critically injured. The scene was indescribable—bodies scattered, vehicles mangled, personal effects strewn across the ground. I remember later hearing that the head of the suicide bomber was recovered more than 100 meters away from the blast, a grim testament to the sheer force of the explosion.
I was in my office at the Naval and Maritime Academy when my mobile phone rang. A young midshipman from the 21st intake called, his voice trembling: “Sir, there was a huge explosion at the convoy point! Many are dead … my batch mate Wijesundara is among them.” I immediately jumped into my jeep with my escort Chief Petty Officer and driver and rushed to Digampathana, relying on every ounce of my driving skill to reach the scene. The journey, which usually took little more than an hour, felt endless that day, each passing mile weighed down by dread.
When I arrived, I was confronted with a sight that no training can prepare you for. The injured were being rushed to Dambulla Hospital, where doctors and nurses worked tirelessly, improvising in ways that saved lives despite the overwhelming chaos. I went back to the site after visiting the hospital. The remains of our naval personnel were scattered across the ground, and someone had begun collecting weapons and protective gear. I immediately contacted Surgeon Rear Admiral Nico Jayasekara and received his instructions: collect all body parts in separate bags and transport them to the Trincomalee Naval Hospital mortuary. This gruesome work had to be done with care and dignity, and it filled the icebox in my vehicle. Through DNA testing initiated by Rear Admiral Nico, we were able to identify every naval personnel lost that day, bringing some closure to grieving families.
The Navy Commander at the time, Vice Admiral Wasantha Karannagoda, was devastated. I had worked closely with him and knew how deeply he cared for his men. He ensured that the fallen were honoured with full ceremonial naval funerals at Welisara Naval Base, attended by families and comrades. Sixty-seven funerals were conducted in a single day—a number that still haunts me.
The Digampathana attack remains the largest single loss of naval life in our history. It was a day of sorrow, but also a day that reinforced our resolve. The tragedy galvanized the Navy to target the LTTE Sea Tiger wing with renewed determination and reshaped our maritime operations forever. Every time I think of that day, I remember not just the lives lost, but the courage, professionalism, and dedication of those who survived, those who treated the injured, and those who ensured the fallen were honored properly. May the souls of our naval hero’s rest in peace, their sacrifice guiding us and inspiring generations of naval personnel to come.
Features
‘Murder at Whitby Abbey’
Tales of Mystery and Suspense – 24
I was intrigued by the title of a book I found in a book drop at the condominium of a friend, Murder at Whitby Abbey, and I brought it home with me though I will not be able to return it in the near future. It was described on the cover page as ‘a standout in the crowded medieval mystery field’, though I fear I do not know of other books in this field, apart from the Cadfael series, which I have dealt with earlier.
The book, by Cassandra Clark, is set during the reign of Richard II and has as a backdrop his precarious position, which led to his being replaced, and murdered, by his cousin Henry, who reigned as Henry IV. It is a gloomy book, the action taking place in the twelve days of Christmas leading up to the Epiphany. And the gloom is pervasive, even though this is supposed to be a time of festivity, with mummers performing, and many of those in the guest house where the heroine stays going to town to enjoy themselves, with much drinking and much music, which also fills the guesthouse.
The heroine Hildegarde is a nun, sent to try to acquire a relic being sold by Whitby Abbey, though this was also a penance set by the Abbot of the monastery that governed her abbess because she had had sex with a man. Soon after she and her companions reach the Abbey set high on a cliff, she finds that there are other bidders, and soon suspects that the hierarchy, not perhaps the Abbot who seems a weakling, but his rapacious bursar, is determined to make money, and not above creating false relics to sell to several aspirants.
After Hildegarde and her Cistercian companions – Whitby is a Benedictine Foundation – two monks, Gregory and Egbert, and a young priest Mark, reach the abbey, they find that Aelwyn, a monk they had met on their way to the guesthouse had died. This was in the apple store, and they realize, when they find the surplices of novices stuffed into the air vents, that he had been left to suffocate in the overwhelming scent of apples.
The Cistercians are asked to look into the death, perhaps because they are likely to get no cooperation from the Abbey folk, but perhaps because those in charge are keen to know what happened. And the infirmarer, an old monk, suggests Hildegarde talk to a man called Edred who worked for the bursar, and had been a friend of Aelwyn’s. But Edred too is killed, before he can keep an appointment he had made with Hildegarde, drowned in a pool near the farmhouse of the Abbey.
Meanwhile tensions arise between the fisherfolk and the abbey for the bursar wants to charge them for using the beach that technically belongs to the abbey to dry their fish and their nets. This leads to physical battles, when the guards used by the abbey, under the command it seems of the bursar whose determination to make money is not resisted by the abbot and the prior, try to storm the area where the fishermen live.
Hildegard finds out more about what had happened through two youngsters, one of whom Torold is the son of Aelwyn by a woman who worked as a prostitute for a cartel, and with whom Mark fell in love. The other works on the farm and had seen Edred meet someone near the pool, after which that someone left the place by himself. And the boy had also found in the pool a sort of dagger with the seal of the abbey.
He and his dog, and Torold who follows her, rescue Hildegarde from a man at arms who has waylaid her and tries to rape her earlier. Escaping into the abbey she was nearly been raped then by the bursar, but she managed to escape, in the process setting fire to him and the muniments room, which led, when he was rescued, to the discovery of a box with the money he said had been stolen, blame being cast on both Aelwyn and Edred.
Matters come to a head when the fisherfolk try to storm the abbey, being resisted by the men at arms stationed on the towers. But then Hildegarde realizes that behind the murders was the bursar’s clerk, whom she pursued to the cathedral. There is great drama then as she escapes from him when he tries to kill her, and then from the man at arms who had tried to both rape and kill her, but they both fall from the scaffolding she had climbed, the latter coming from a tower where he had been stationed.
Both of them think they run the rapacity of the abbey, the latter claiming to work for the nobles opposed to Richard, who is presented throughout the book as devoted to his subjects, not to power or money. But though the villains die, the bursar continues, having got over the hysteria the fire had caused and his acknowledgment then of guilt – and though the abbot and the prior seem less vicious, whether they will be able to assert themselves is questionable.
Before the climax, when the others in the guesthouse were leaving, Hildegarde found that two of them were in possession of the relic, for which they seem to have paid well. Hildegarde herself had made a derisory offer, but before she leaves the abbot gives her the relic, perhaps in gratitude for what she and her fellow Cistercians had discovered, the abbey having made as much money as it needed and more from the gullible other buyers.
Mark’s inamorata is saved from the stews because she moves in with Edred’s widow whom the bursar had thrown out of the rooms he occupied when her husband was found dead. Hildegarde had paid for lodgings, in a house run by the man who ran the brothels, but he had a kindly side and was going to finance them to make nets for the fishermen.
So, the Cistercians set off for their home as swiftly as they can to get there on the day of the Epiphany, having stopped en route to pray for King Richard whose birthday it was.
-
News5 days agoSri Lanka escalates anti-graft drive with Shiranthi’s jailing
-
News6 days agoNPP govt. reminded of its responsibilities as US warship leaves Colombo
-
Latest News6 days agoFarhan, Sadaqat help Pakistan ace 183 chase to go 1-0 up
-
Latest News4 days agoFarhan and Sadaqat help Pakistan seal series in style
-
News5 days agoIranian ships stranded, Lanka fears US sanctions
-
Latest News3 days agoNissanka’s return headlines Sri Lanka’s Test squad against Pakistan
-
News6 days agoInterdicted top House official Kularatne receives special recognition in Mexican Parliament
-
Features4 days agoIntake 16: 45 years of duty and honour

