News
CEB: Corrective measures taken to prevent power failures
by Ifham Nizam
The Ceylon Electricity Board (CEB) yesterday said it had adopted a series of immediate and long-term corrective measures to prevent future power failures following the nationwide blackout on 09 Feb.
The power failure, which occurred at 11:13 AM, was attributed to a system-wide disturbance at the 33kV Panadura Grid Substation, exacerbated by the high penetration of solar photovoltaic (PV) generation.
CEB’s Media Spokesman, Eng. M.H. Dhammike Wimalaratne, said the grid had low system inertia due to the dominance of non-synchronous solar PV power, making it highly vulnerable to faults. “The sharp voltage drop led to cascading disconnections, ultimately causing a total power failure,” he noted.
In response, CEB has taken immediate corrective measures, including keeping more synchronous generators online and operating selected gas turbines in synchronous condenser mode to enhance voltage stability. “We are also implementing necessary curtailments on ground-mounted solar PV during low-demand periods to prevent instability,” Wimalaratne added.
Looking ahead, CEB is accelerating efforts to adjust rooftop solar PV inverter settings, introduce special industrial tariffs to balance demand, and promote Battery Energy Storage Systems (BESS) to enhance grid resilience. Additionally, long-term strategies include deploying grid-forming inverters, installing emergency backup generators at Norochcholai, and expediting the Maha Oya Pumped Hydro Project—a 600 MW storage facility aimed at improving energy security.
Despite the challenges, CEB reassures the public of its commitment to a reliable power supply. “As we transition to a renewable energy-driven system, we are implementing proactive measures to ensure a stable and future-ready grid,” Wimalaratne emphasized.
The recent blackout underscores the need for grid modernization, with CEB’s swift response highlighting the urgency of balancing renewable energy integration with grid stability.
Latest News
Heat Index likely to increase up to ‘Caution level’ at some places in the Western, Sabaragamuwa, Southern and North-western provinces and in Monaragala and Mannar districts
Warm Weather Advisory
Issued by the Natural Hazards Early Warning Centre of the Department of Meteorology at 3.30 p.m. on 12 March 2026, valid for 13 March 2026.
Heat index, the temperature felt on human body is likely to increase up to ‘Caution level’ at some places in Western, Sabaragamuwa, Southern and North-western provinces and in
Monaragala and Mannar districts.
The Heat Index Forecast is calculated by using relative humidity and maximum temperature and this is the condition that is felt on your body. This is not the forecast of maximum temperature. It is generated by the Department of Meteorology for the next day period and prepared by using global numerical weather prediction model data.

Effect of the heat index on human body is mentioned in the above table and it is prepared on
the advice of the Ministry of Health and Indigenous Medical Services.
ACTION REQUIRED
Job sites: Stay hydrated and takes breaks in the shade as often as possible.
Indoors: Check up on the elderly and the sick.
Vehicles: Never leave children unattended.
Outdoors: Limit strenuous outdoor activities, find shade and stay hydrated.
Dress: Wear lightweight and white or light-colored clothing.
Note:
In addition, please refer to advisories issued by the Disaster Preparedness & Response Division, Ministry of Health in this regard as well. For further clarifications please contact 011-7446491.
News
Govt. bends rules, lowers coal standards in favour of errant company: FSP
The Frontline Socialist Party (FSP) yesterday accused the government of trying to award another tender to the Indian company that supplied low-grade coal to the Norochcholai Power Plant and failed to deliver the stipulated amount of coal according to schedule.
The allegation was made by the Education Secretary of the Progressive Socialist Party, Pubudu Jayagoda, during media briefing at the party office in Nugegoda last afternoon.
Jayagoda said that in September 2025, the government had awarded a tender to the Indian company Trident Chemphar to supply 25 coal shipments for electricity generation in 2026.
In August 2025, it was confirmed that the coal delivered by the company was substandard. The company also failed to supply coal on schedule. Although the first shipment was expected in the second week of December 2025, it arrived at the end of the month. By mid-March, only 12 ships had arrived, and biweekly deliveries have been disrupted, putting Sri Lanka at risk of a severe energy shortage.
On 11 March, the government called a sudden spot tender for five coal shipments. Four companies submitted bids, and they include Trident Chemphar. FSP criticiced awarding the tender to the same discredited company, saying it was unethical and could trigger a major national crisis, as the company had failed to supply quality coal reliably in the past.
Previously, coal quality was strictly measured, with a “Reject Value”. But now to help the errant supplier the term of Reject Value has now been omitted altogether and replaced with a new term ‘Minimum Value’ setting it as the minimum calorific threshold—coal producing less than 5,900 kilocalories per kilogram was rejected, and coal with ash content above 16% was also discarded.
However, the government is now reportedly lowering these standards, accepting substandard coal, and changing tender specifications to accommodate the company.
Jayagoda castigated the latest stunt coming especially at a time when the world faces war and oil shortages. Diesel meant for electricity generation is being diverted to school buses, public transport, and emergency vehicles, leaving households at risk of prolonged blackouts. Even if diesel is imported, electricity tariffs could skyrocket.
News
Lanka requests diesel from India
The Indian Ministry of External Affairs has said it is considering requests for diesel supplies from neighbouring countries, including Sri Lanka, Bangladesh and the Maldives.
Speaking to the Press Trust of India, Ministry Spokesperson Randhir Jaiswal noted that India was a major exporter of refined petroleum products in the region. He confirmed that Bangladesh had formally requested a diesel supply, which is currently under review.
He said that diesel exports to Bangladesh had largely continued since 2017, but any new allocations would take into account India’s refining capacity, domestic demand, and overall fuel availability.
Jaiswal added that similar requests from Sri Lanka and the Maldives were also being considered, with India’s own energy requirements forming a key part of the decision-making process.
-
News6 days agoPeradeniya Uni issues alert over leopards in its premises
-
News4 days agoRepatriation of Iranian naval personnel Sri Lanka’s call: Washington
-
News6 days agoWife raises alarm over Sallay’s detention under PTA
-
News3 days agoProf. Dunusinghe warns Lanka at serious risk due to ME war
-
Features4 days agoWinds of Change:Geopolitics at the crossroads of South and Southeast Asia
-
Latest News6 days agoHeat Index at ‘Caution Level’ in the Sabaragamuwa province and, Colombo, Gampaha, Kurunegala, Anuradhapura, Vavuniya, Hambanthota and Monaragala districts
-
Features6 days agoThe final voyage of the Iranian warship sunk by the US
-
Sports2 days agoRoyal start favourites in historic Battle of the Blues