Court moved against construction of highway across wetland

Published

on

By Ifham Nizam

A case had been filed against the construction of the 3.15 km Orugudawatta-Athurugiriya highway, running through the Thalangama-Avarihena wetland, the Centre for Environmental Justice legal team said.

The construction of roads through a wetland was to be carried out under the National Environment Act 1487/10 Gazette. However, an environmental impact assessment (EIA) report has not been submitted for the project’s second phase. This is an unauthorised practice as per Schedule II of the Gazette.

The suit was filed on 11.02.2021 by two petitioners, including the Centre for Environmental Justice (CEJ), under the powers conferred by Sections 24 C and 24D of the Environment Act No. 47 of1980.The proposed highway is to run through the Talangama/Avarihena wetland, which was declared by Gazette No. 1487/10 dated March 2007 as an Environmental Protection area.

The petitioners have requested the Court to issue a writ of prohibition against the respondents for allowing the construction to pass through the Talangama Wetland.However, the respondents have argued that Gazette No. 1487/10 has been amended by Gazette No.2237/7 issued by the Minister, and since the case has been filed based on Gazette No.1487/10 there is no need to maintain this case further.

After considering the facts, the Court of Appeal ordered, on January 19, 2022, that according the Third Schedule (n) of Gazette No. 2237/7, the construction of the expressway in question should not harm the ecologically protected area.

Since the petitioners have been able to prove their case prima facie that the minister changed the original order to the environmental protection zone, the court allowed the petitioner to continue the petition. This was followed by a petition filed by the Road Development Authority and its Chairman on 25 February 2022.

A petition was filed on December 23, 2020, by the Centre for Environmental Justice and Senior Advisor/Director, Hemantha Withanage regarding the illegal activities around the Muthurajawela Sanctuary. The Muthurajawela North Swamp area has been declared as a wetland sanctuary as per the Special Gazette No. 947/13 and its induction zone has also been declared an “Environment Protection Zone’ in 2004 under Sections 24C and 24D of the National Environment Act Gazette No. 1466/26 dated 13 Oct 2006.The petitioners request an interim restraining order to stop activities in the vicinity of the

Muthurajawela Sanctuary violating the Agricultural Development Act No. 46 of 2000, for carrying out activities related to the Extraordinary Gazette No. 772/22 dated 24.06.1993 without an environmental assessment report, carrying out activities that are prohibited in a sanctuary under Section 7 of the Wildlife and Flora Protection Ordinance. They also request to mark the physical boundaries of the Muthurajawela Sanctuary and to issue a writ of mandamus to implement the National Policy on Wetlands.

In the petition, the petitioners sought a writ of mandamus to act in terms of the Fauna and Flora Protection Ordinance in relation to the damage caused. Giving the order dated 04 April 2022, the Court of Appeal directs the Director General of the Survey Department and the Inspector General of Police to mark the physical boundaries of the Muthurajawela Sanctuary and the Environmental Protection Zone. Also, the Central Environment Authority and the Department of Wildlife Conservation have been ordered to install notice boards in those zones and the Police Commissioner has been ordered to take steps to protect the relevant boundaries and boards and to take steps to prevent illegal activities from taking place in the Muthurajawela Sanctuary and the Environmental Protection Zone.